Filters
Question type

Study Flashcards

Scarlett Company has a direct material standard of 3 gallons of input at a cost of $5 per gallon.During July,Scarlett Company purchased and used 7,500 gallons.The direct material quantity variance was $750 unfavorable and the direct material price variance was $3,000 favorable.What price per gallon was paid for the purchases?


A) $5.00
B) $5.40
C) $4.60
D) $2.50

E) All of the above
F) A) and B)

Correct Answer

verifed

verified

The price variance for direct labor is called the direct labor rate variance.Because the price of direct labor is called the direct labor rate,the price variance for labor is called the direct labor rate variance.

A) True
B) False

Correct Answer

verifed

verified

In a standard cost system,overhead is applied per unit by multiplying the standard overhead rate times the standard quantity of the cost driver.This is a key difference between the standard cost system and the normal cost system - overhead is applied based on the standard quantity of the cost driver rather than the actual quantity.

A) True
B) False

Correct Answer

verifed

verified

The difference between budgeted volume and practical capacity,multiplied by the fixed overhead rate,is the


A) Expected (planned) capacity variance.
B) Unexpected (unplanned) capacity variance.
C) Total capacity variance.
D) Volume variance.

E) None of the above
F) A) and B)

Correct Answer

verifed

verified

Venus Company applies overhead based on direct labor hours.The variable overhead standard is 10 hours at $3.50 per hour.During October,Venus Company spent $157,600 for variable overhead.47,440 labor hours were used to produce 4,800 units.What is the over- or underapplied variable overhead?


A) $10,400 overapplied
B) $8,440 overapplied
C) $8,440 underapplied
D) $1,960 overapplied

E) None of the above
F) B) and C)

Correct Answer

verifed

verified

The formula SP × (SQ - AQ) is the


A) direct materials spending variance.
B) direct materials volume variance.
C) direct materials price variance.
D) direct materials quantity variance.

E) All of the above
F) C) and D)

Correct Answer

verifed

verified

The difference between the actual price and the standard price,multiplied by the actual quantity of materials purchased is the


A) direct materials spending variance.
B) direct materials volume variance.
C) direct materials price variance.
D) direct materials quantity variance.

E) None of the above
F) B) and D)

Correct Answer

verifed

verified

Cooper Company has a direct material standard of 2 gallons of input at a cost of $7.50 per gallon.During July,Cooper Company purchased and used 13,000 gallons,paying $93,200.The direct materials quantity variance was $1,500 unfavorable.How many units were produced?


A) 13,000 units
B) 6,600 units
C) 6,214 units
D) 6,400 units

E) A) and D)
F) B) and C)

Correct Answer

verifed

verified

In a standard cost system,an unfavorable variance will appear as


A) a credit entry.
B) a debit entry.
C) either a debit or a credit entry.
D) variances do not affect journal entries.

E) B) and D)
F) None of the above

Correct Answer

verifed

verified

The difference between the actual quantity and the standard quantity,multiplied by the standard price is the


A) direct materials spending variance.
B) direct materials volume variance.
C) direct materials price variance.
D) direct materials quantity variance.

E) B) and C)
F) A) and B)

Correct Answer

verifed

verified

Jupiter Co.applies overhead based on direct labor hours.The variable overhead standard is 4 hours at $12 per hour.During February,Jupiter Co.spent $113,400 for variable overhead.9,150 labor hours were used to produce 2,400 units.What is the variable overhead rate variance?


A) $3,600 unfavorable
B) $3,600 favorable
C) $5,400 favorable
D) $1,800 favorable

E) All of the above
F) A) and D)

Correct Answer

verifed

verified

The fixed overhead volume variance is the difference between


A) Actual fixed overhead and budgeted fixed overhead.
B) Actual fixed overhead and applied fixed overhead.
C) Applied fixed overhead and budgeted fixed overhead.
D) Actual fixed overhead and the standard fixed overhead rate times actual cost driver.

E) A) and D)
F) A) and C)

Correct Answer

verifed

verified

A fixed overhead rate based on _______________ highlights for management attention the cost of unutilized capacity.


A) budgeted production
B) practical capacity
C) utilized capacity
D) actual production

E) B) and C)
F) C) and D)

Correct Answer

verifed

verified

Madrid Co.has a direct labor standard of 4 hours per unit of output.Each employee has a standard wage rate of $11 per hour.During February,Madrid Co.paid $99,500 to employees for 9,150 hours worked.2,400 units were produced during February.What is the direct labor efficiency variance?


A) $1,150 favorable
B) $4,950 favorable
C) $6,100 favorable
D) $302 favorable

E) C) and D)
F) None of the above

Correct Answer

verifed

verified

The formula SR × (SH - AH) is the


A) direct labor spending variance.
B) direct labor volume variance.
C) direct labor rate variance.
D) direct labor efficiency variance.

E) B) and C)
F) A) and D)

Correct Answer

verifed

verified

Venus Company applies overhead based on direct labor hours.The variable overhead standard is 10 hours at $3.50 per hour.During October,Venus Company spent $157,600 for variable overhead.47,440 labor hours were used to produce 4,800 units.What is the variable overhead rate variance?


A) $8,440 favorable
B) $1,960 favorable
C) $10,400 favorable
D) $1,960 unfavorable

E) B) and D)
F) A) and C)

Correct Answer

verifed

verified

An ideal standard is one which can be achieved only under perfect conditions.This is the definition of an ideal standard.

A) True
B) False

Correct Answer

verifed

verified

The variable overhead rate variance is the difference between the actual variable overhead rate and the standard variable overhead rate multiplied by the actual value of the cost driver.This is the formula for the variable overhead rate variance.

A) True
B) False

Correct Answer

verifed

verified

The difference between the actual labor rate and the standard labor rate,multiplied by the actual labor hours is the


A) direct labor spending variance.
B) direct labor volume variance.
C) direct labor rate variance.
D) direct labor efficiency variance.

E) All of the above
F) A) and D)

Correct Answer

verifed

verified

The production manager is typically responsible for the direct labor rate variance.It is difficult to hold an individual manager responsible for the direct labor rate variance because many factors can influence the wage rate.

A) True
B) False

Correct Answer

verifed

verified

Showing 21 - 40 of 100

Related Exams

Show Answer