Filters
Question type

Study Flashcards

Easily attainable standards are the best for motivating individuals to work hard.Tight but attainable standards are the best for motivating individuals to work hard.

A) True
B) False

Correct Answer

verifed

verified

Venus Company applies overhead based on direct labor hours.The variable overhead standard is 10 hours at $3.50 per hour.During October,Venus Company spent $157,600 for variable overhead.47,440 labor hours were used to produce 4,800 units.What is the variable overhead efficiency variance?


A) $8,440 favorable
B) $1,960 favorable
C) $10,400 favorable
D) $1,960 unfavorable

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

A quantity standard is


A) the total dollar amount that a company expects to spend to achieve a given level of output.
B) a form that shows what the company should spend to make a single unit of product.
C) the price that should be paid for a specific quantity of input.
D) the amount of input that should be used in each unit of product or service.

E) A) and B)
F) All of the above

Correct Answer

verifed

verified

Whitman has a direct labor standard of 2 hours per unit of output.Each employee has a standard wage rate of $22.50 per hour.During July,Whitman paid $94,750 to employees for 4,445 hours worked.2,350 units were produced during July.What is the flexible budget amount for direct labor?


A) $105,750
B) $189,500
C) $200,025
D) $211,500

E) None of the above
F) All of the above

Correct Answer

verifed

verified

The difference between the actual variable overhead rate and the standard variable overhead rate,multiplied by the actual amount of the cost driver,is the


A) variable overhead rate variance.
B) variable overhead efficiency variance.
C) variable overhead volume variance.
D) over- or underapplied variance.

E) None of the above
F) B) and C)

Correct Answer

verifed

verified

Delaware Corp.prepared a master budget that included $21,360 for direct materials,$33,600 for direct labor,$18,000 for variable overhead,and $46,440 for fixed overhead.Delaware Corp.planned to sell 4,000 units during the period,but actually sold 4,300 units.How much would variable overhead cost be on a flexible budget for the period based on actual sales?


A) $16,745
B) $18,000
C) $19,350
D) $46,440

E) A) and B)
F) All of the above

Correct Answer

verifed

verified

In a standard cost system,a favorable variance will appear as


A) a credit entry.
B) a debit entry.
C) either a debit or a credit entry.
D) variances do not affect journal entries.

E) A) and D)
F) All of the above

Correct Answer

verifed

verified

Melrose Inc.uses standard costing.Last period,its flexible budget for labor was $144,000.The direct labor rate variance was $5,000 favorable,and the direct labor efficiency variance was $6,000 unfavorable.In the journal entry to record the use of direct labor,the amount credited to wages payable would be


A) $144,000
B) $145,000
C) $150,000
D) $151,000

E) All of the above
F) A) and D)

Correct Answer

verifed

verified

Comparing the master budget with the flexible budget creates a


A) quantity variance.
B) volume variance.
C) spending variance.
D) price variance.

E) None of the above
F) A) and B)

Correct Answer

verifed

verified

The standard costs are summarized on a:


A) static cost card.
B) flexible budget card.
C) standard cost card.
D) standard static carD.The standard cost card shows what the company should spend to make a single unit of product based on expected production and sales for the coming period.

E) A) and C)
F) All of the above

Correct Answer

verifed

verified

Warner Co.has budgeted fixed overhead of $150,000.Practical capacity is 6,000 units,and budgeted production is 5,000 units.During February,4,800 units were produced and $155,600 was spent on fixed overhead.What is the expected (planned) capacity variance?


A) $5,600 unfavorable
B) $25,000 unfavorable
C) $30,000 unfavorable
D) $35,600 unfavorable

E) A) and D)
F) A) and C)

Correct Answer

verifed

verified

The difference between budgeted volume and practical capacity,multiplied by the fixed overhead rate,is the


A) Expected (planned) capacity variance.
B) Unexpected (unplanned) capacity variance.
C) Total capacity variance.
D) Volume variance.

E) A) and D)
F) C) and D)

Correct Answer

verifed

verified

Tucker Co.has budgeted fixed overhead of $225,000 based on budgeted production of 7,500 units.During February,7,200 units were produced and $233,400 was spent on fixed overhead.What is the fixed overhead spending variance?


A) $8,400 unfavorable
B) $9,000 unfavorable
C) $17,400 unfavorable
D) $600 favorable

E) A) and D)
F) C) and D)

Correct Answer

verifed

verified

Tulip Inc.uses standard costing,and its manufacturing standards are as follows: 2 pounds of materials at $13 per pound,and 3 hours of labor at $10 per hour.Budgeted production last period was 5,000 units,and actual production was 4,800 units.Last period,Tulip purchased and used 9,800 pounds of materials for $135,000,and used 15,000 labor hours,costing $145,000.What is the journal entry to record the use of materials? Tulip Inc.uses standard costing,and its manufacturing standards are as follows: 2 pounds of materials at $13 per pound,and 3 hours of labor at $10 per hour.Budgeted production last period was 5,000 units,and actual production was 4,800 units.Last period,Tulip purchased and used 9,800 pounds of materials for $135,000,and used 15,000 labor hours,costing $145,000.What is the journal entry to record the use of materials?   A) Option A B) Option B C) Option C D) Option D


A) Option A
B) Option B
C) Option C
D) Option D

E) A) and D)
F) All of the above

Correct Answer

verifed

verified

Melrose Inc.uses standard costing.Last period,it spent $145,000 for labor.The direct labor rate variance was $5,000 favorable,and the direct labor efficiency variance was $6,000 unfavorable.In the journal entry to record the use of direct labor,the amount debited to cost of goods sold would be


A) $144,000
B) $145,000
C) $150,000
D) $151,000

E) None of the above
F) A) and B)

Correct Answer

verifed

verified

Tulip Inc.uses standard costing,and its manufacturing standards are as follows: 2 pounds of materials at $13 per pound,and 3 hours of labor at $10 per hour.Budgeted production last period was 5,000 units,and actual production was 4,800 units.Last period,Tulip purchased and used 9,800 pounds of materials for $135,000,and used 15,000 labor hours,costing $145,000.What is the journal entry to record direct labor costs? Tulip Inc.uses standard costing,and its manufacturing standards are as follows: 2 pounds of materials at $13 per pound,and 3 hours of labor at $10 per hour.Budgeted production last period was 5,000 units,and actual production was 4,800 units.Last period,Tulip purchased and used 9,800 pounds of materials for $135,000,and used 15,000 labor hours,costing $145,000.What is the journal entry to record direct labor costs?   A) Option A B) Option B C) Option C D) Option D


A) Option A
B) Option B
C) Option C
D) Option D

E) A) and D)
F) B) and C)

Correct Answer

verifed

verified

After selling 4,300 units during the period,Dole Corp.prepared a flexible budget that included $22,962 for direct materials,$36,120 for direct labor,$19,350 for variable overhead,and $46,440 for fixed overhead.Dole originally planned its master budget based on sales of 4,000 units.What would total costs have been on the master budget?


A) $111,070
B) $119,400
C) $124,872
D) $116,160

E) A) and D)
F) B) and C)

Correct Answer

verifed

verified

The flexible budget can be used as a benchmark for evaluating performance after the fact,as part of the control process.The flexible budget can be used as part of the planning process to predict how the budget will change under various scenarios.The flexible budget can also be used as a benchmark for evaluating performance after the fact as part of the control process.

A) True
B) False

Correct Answer

verifed

verified

When preparing a flexible budget,fixed costs should remain the same as on the master budget.Fixed costs remain the same regardless of volume,which is the only change that occurs from master to flexible budget.

A) True
B) False

Correct Answer

verifed

verified

To foster continuous improvement,standards should ________________ in difficulty over time.


A) remain stable
B) increase
C) decrease
D) idealize

E) C) and D)
F) B) and D)

Correct Answer

verifed

verified

Showing 41 - 60 of 100

Related Exams

Show Answer