A) $6,508.54
B) -$320.81
C) $560.24
D) $1,410.10
E) $8,211.15
Correct Answer
verified
Multiple Choice
A) $26,064.12
B) $30,759.80
C) $29,848.20
D) $28,309.40
E) $30,630.60
Correct Answer
verified
Multiple Choice
A) $2,400
B) $2,100
C) -$2.400
D) -$2,100
E) $3,300
Correct Answer
verified
Multiple Choice
A) -$1,806.67
B) $640.89
C) $1,311.16
D) $1,409.80
E) -$2,276.60
Correct Answer
verified
Multiple Choice
A) determines the impact a $1 change in sales has on a project's internal rate of return.
B) determines which variable has the greatest impact on a project's net present value.
C) helps determine the reasonable range of expectations for a project's anticipated outcome.
D) evaluates a project's net present value while sensitivity analysis evaluates a project's internal rate of return.
E) determines the absolute worst and absolute best outcome that could ever occur.
Correct Answer
verified
Multiple Choice
A) a sunk cost.
B) an opportunity cost.
C) recouped in the first year of the project.
D) recouped at the end of the project.
E) depreciated to a zero balance over the life of the project.
Correct Answer
verified
Multiple Choice
A) sensitivity analysis.
B) erosion planning.
C) scenario analysis.
D) benefit planning.
E) opportunity evaluation.
Correct Answer
verified
Multiple Choice
A) Ability to wait until the economy improves before making the investment
B) Ability to immediately shut down a project should the project become unprofitable
C) Option to increase production beyond that initially projected
D) Option to place the investment on hold until a more favorable discount rate becomes available
E) Option to discontinue a project at the end of its intended life
Correct Answer
verified
Multiple Choice
A) most likely outcome for a project.
B) reasonable range of project outcomes.
C) variable that has the greatest effect on a project's outcome.
D) effect that a project's initial cost has on the project's net present value.
E) change in a project's net present value given a stated change in projected sales.
Correct Answer
verified
Multiple Choice
A) $742,519.10
B) $726,000.00
C) $832,056.60
D) $791,504.40
E) $887,560.15
Correct Answer
verified
Multiple Choice
A) may overestimate the internal rate of return on a project.
B) may underestimate the net present value of a project.
C) ignores the ability of a manager to increase output after a project has been implemented.
D) is the same as ignoring all strategic options.
E) ignores the value of discontinuing a project early.
Correct Answer
verified
Multiple Choice
A) -$110.50
B) -$64.10
C) $909.50
D) $209.00
E) $660.50
Correct Answer
verified
Multiple Choice
A) eroded cash flows.
B) deviated projections.
C) incremental cash flows.
D) directly impacted flows.
E) opportunity cash flows.
Correct Answer
verified
Multiple Choice
A) $0
B) $57,037.75
C) $28,528.50
D) $85,547.00
E) $96,250.00
Correct Answer
verified
Multiple Choice
A) -$49,000
B) -$47,000
C) -$3,000
D) -$13,000
E) -$24,000
Correct Answer
verified
Multiple Choice
A) 15.51 percent
B) 15.98 percent
C) 20.12 percent
D) 17.64 percent
E) 17.99 percent
Correct Answer
verified
Multiple Choice
A) $19,776.80
B) $18,846.67
C) $24,223.20
D) $20,408.20
E) $25,153.33
Correct Answer
verified
Multiple Choice
A) 8.32 percent
B) 8.68 percent
C) 7.47 percent
D) 11.09 percent
E) 12.14 percent
Correct Answer
verified
Multiple Choice
A) $38,578,064
B) $39,822,128
C) $38,216,051
D) $41,802,137
E) $40,864,538
Correct Answer
verified
Multiple Choice
A) $218,336.00
B) $201,015.00
C) $261,015.50
D) $371,615.50
E) $314,450.00
Correct Answer
verified
Showing 21 - 40 of 116
Related Exams