A) No; The IRR exceeds the required return.
B) No; The IRR is less than the required return.
C) Yes; The IRR exceeds the required return.
D) Yes; The IRR equals the required return.
E) No; The IRR equals the required return.
Correct Answer
verified
Multiple Choice
A) The net present value indicates accept while the internal rate of return indicates reject.
B) Payback indicates acceptance.
C) The payback decision rule could override the accept decision indicated by the net present value.
D) The payback rule will automatically be ignored since both the net present value and the internal rate of return indicate an accept decision.
E) The net present value decision rule is the only rule that matters when making the final decision.
Correct Answer
verified
Multiple Choice
A) 12.79 percent
B) 11.82 percent
C) 10.35 percent
D) 11.69 percent
E) 10.14 percent
Correct Answer
verified
Multiple Choice
A) may produce multiple rates of return when cash flows are conventional.
B) is best used when comparing mutually exclusive projects.
C) is rarely used in the business world today.
D) is principally used to evaluate small dollar projects.
E) is easy to understand.
Correct Answer
verified
Multiple Choice
A) 13.94 percent
B) 14.91 percent
C) 15.66 percent
D) 14.75 percent
E) 15.31 percent
Correct Answer
verified
Multiple Choice
A) net present value period.
B) internal return period.
C) payback period.
D) discounted profitability period.
E) discounted payback period.
Correct Answer
verified
Multiple Choice
A) net present value.
B) internal rate of return.
C) accounting return.
D) profitability index.
E) payback period.
Correct Answer
verified
Multiple Choice
A) required return.
B) zero-sum rate.
C) present value rate.
D) break-even rate.
E) crossover rate.
Correct Answer
verified
Multiple Choice
A) Yes; The IRR exceeds the required return.
B) Yes; The IRR is less than the required return.
C) No; The IRR is less than the required return.
D) No; The IRR exceeds the required return.
E) You should not apply the IRR rule in this case.
Correct Answer
verified
Multiple Choice
A) neither project will be accepted if the discount rate is less than 11.7 percent.
B) both projects have a negative NPV at discount rates greater than 11.7 percent.
C) both projects provide an internal rate of return of 11.7 percent.
D) both projects have a zero NPV at a discount rate of 11.7 percent.
E) the project that is acceptable at a discount rate of 11 percent should be rejected at a discount rate of 12 percent.
Correct Answer
verified
Multiple Choice
A) would need to commence on the same day.
B) have the same initial start-up costs.
C) both require the total use of the same limited resource.
D) both have negative cash outflows at time zero.
E) have the same life span.
Correct Answer
verified
Multiple Choice
A) Accept A at both discount rates
B) Accept A at 11.7 percent and neither at 13.5 percent
C) Accept B at both discount rates
D) Accept both at 11.7 percent and neither at 13.5 percent
E) Accept B at 11.7 percent and neither at 13.5 percent
Correct Answer
verified
Multiple Choice
A) some positive net present value projects to be rejected.
B) the most liquid projects to be rejected in favor of the less liquid projects.
C) projects to be incorrectly accepted due to ignoring the time value of money.
D) a firm to become more long-term focused.
E) some projects to be accepted which would otherwise be rejected under the payback rule.
Correct Answer
verified
Multiple Choice
A) 2.31 years
B) 2.45 years
C) 2.55 years
D) 2.87 years
E) Never
Correct Answer
verified
Multiple Choice
A) 7.36 years
B) 5.28 years
C) 5.58 years
D) 8.13 years
E) Never
Correct Answer
verified
Multiple Choice
A) have two net present value profiles.
B) have operational ambiguity.
C) create a mutually exclusive investment decision.
D) produce multiple economies of scale.
E) have multiple rates of return.
Correct Answer
verified
Multiple Choice
A) .93; accept
B) 1.07; accept
C) 1.02; accept
D) .93; reject
E) 1.07 reject
Correct Answer
verified
Multiple Choice
A) always accept Project A.
B) be indifferent to the projects at any discount rate above 13.1 percent.
C) always accept Project A if the required return exceeds the crossover rate.
D) accept Project B only when the required return is equal to the crossover rate.
E) accept Project B if the required return is less than 13.1 percent.
Correct Answer
verified
Multiple Choice
A) 3.73 years
B) 2.51 years
C) 3.13 years
D) 3.51 years
E) 3.94 years
Correct Answer
verified
Multiple Choice
A) 1.98; accept
B) 1.79; accept
C) 2.46; accept
D) 2.02; reject
E) 2.29; reject
Correct Answer
verified
Showing 21 - 40 of 108
Related Exams