A) 4.48 percent
B) 3.13 percent
C) 3.22 percent
D) 3.73 percent
E) 2.88 percent
Correct Answer
verified
Multiple Choice
A) $2,740,563
B) $2,584,798
C) $1,711,052
D) $2,008,051
E) $2,123,008
Correct Answer
verified
Multiple Choice
A) 7.17 percent
B) 6.48 percent
C) 6.62 percent
D) 6.80 percent
E) 7.11 percent
Correct Answer
verified
Multiple Choice
A) company's beta.
B) coupon rate of the company's outstanding bonds.
C) growth rate of the company's dividends.
D) company's marginal tax rate.
E) standard deviation of the company's common stock.
Correct Answer
verified
Multiple Choice
A) Deep Mining only
B) Precious Metals only
C) Both Deep Mining and Precious Metals
D) Neither Deep Mining nor Precious Metals
E) Cannot be determined without further information
Correct Answer
verified
Multiple Choice
A) 13.87 percent
B) 14.06 percent
C) 14.23 percent
D) 13.38 percent
E) 14.50 percent
Correct Answer
verified
Multiple Choice
A) 10.0 percent
B) 9.2 percent
C) 10.9 percent
D) 11.3 percent
E) 11.7 percent
Correct Answer
verified
Multiple Choice
A) 9.41 percent
B) 9.51 percent
C) 8.47 percent
D) 8.27 percent
E) 8.82 percent
Correct Answer
verified
Multiple Choice
A) is determined by the overall risk level of the firm.
B) is dependent upon the source of the funds obtained to fund that project.
C) is dependent upon the firm's overall capital structure.
D) should be applied as the discount rate for all other projects considered by the firm.
E) depends upon how the funds raised for that project are going to be spent.
Correct Answer
verified
Multiple Choice
A) allocate more funds to Division A since it is the larger of the two divisions.
B) fund all of Division B's projects first since they tend to be less risky and then allocate the remaining funds to the Division A projects that have the highest net present values.
C) allocate the company's funds to the projects with the highest net present values based on the company's weighted average cost of capital.
D) assign appropriate, but differing, discount rates to each project and then select the projects with the highest net present values.
E) fund the highest net present value projects from each division based on an allocation of 65 percent of the funds to Division A and 35 percent of the funds to Division B.
Correct Answer
verified
Multiple Choice
A) 4.88 percent
B) 4.16 percent
C) 5.87 percent
D) 4.78 percent
E) 6.05 percent
Correct Answer
verified
Multiple Choice
A) .37
B) .42
C) .56
D) .34
E) .44
Correct Answer
verified
Multiple Choice
A) ignored when analyzing a project because they are a sunk cost.
B) spread over the life of a project thereby reducing the cash flows for each year of the project.
C) considered only when two projects are mutually exclusive.
D) weighted and included in the initial cash flow.
E) totally ignored when internal equity funding is utilized.
Correct Answer
verified
Multiple Choice
A) be accepted immediately.
B) be financed solely with debt in order for the project to have a positive NPV.
C) probably be put on hold until its cost of capital can be lowered.
D) be permanently rejected.
E) probably be expanded.
Correct Answer
verified
Multiple Choice
A) 12.77 percent
B) 12.29 percent
C) 12.67 percent
D) 12.24 percent
E) 12.54 percent
Correct Answer
verified
Multiple Choice
A) is equivalent to the aftertax cost of the outstanding liabilities.
B) should be used as the required return when analyzing any new project.
C) is the return investors require on the total assets of the firm.
D) remains constant when the debt-equity ratio changes.
E) is unaffected by changes in corporate tax rates.
Correct Answer
verified
Multiple Choice
A) $302,400
B) $318,924
C) $280,758
D) $256,700
E) $333,333
Correct Answer
verified
Multiple Choice
A) .28 percent
B) .14 percent
C) .26 percent
D) .12 percent
E) .43 percent
Correct Answer
verified
Multiple Choice
A) cause the project to be improperly evaluated.
B) increase the net present value of the project.
C) increase the project's rate of return.
D) increase the initial cash outflow of the project.
E) have no effect on the present value of the project.
Correct Answer
verified
Multiple Choice
A) 8.50 percent
B) 8.88 percent
C) 8.67 percent
D) 9.29 percent
E) 9.00 percent
Correct Answer
verified
Showing 61 - 80 of 99
Related Exams