A) compound rate.
B) current yield.
C) cost of debt.
D) capital gains yield.
E) cost of capital.
Correct Answer
verified
Multiple Choice
A) The subjective approach assigns a discount rate to each project based on other companies in the same category as the project.
B) Overall, a company makes better decisions when it uses the subjective approach than when it uses its WACC as the discount rate for all projects.
C) Companies will correctly accept or reject every project if they adopt the subjective approach.
D) Mandatory projects should only be accepted if they produce a positive NPV when the overall company WACC is used as the discount rate.
E) The pure play approach should only be used with low-risk projects.
Correct Answer
verified
Multiple Choice
A) 5.83 percent
B) 5.20 percent
C) 4.42 percent
D) 5.67 percent
E) 4.58 percent
Correct Answer
verified
Multiple Choice
A) 1.85 percent
B) 2.16 percent
C) 1.98 percent
D) 2.47 percent
E) 2.39 percent
Correct Answer
verified
Multiple Choice
A) 18.74 percent
B) 17.13 percent
C) 10.38 percent
D) 19.53 percent
E) 11.79 percent
Correct Answer
verified
Multiple Choice
A) 10.96 percent
B) 11.67 percent
C) 12.06 percent
D) 11.38 percent
E) 11.57 percent
Correct Answer
verified
Multiple Choice
A) $349,019
B) $324,324
C) $312,386
D) $318,513
E) $324,706
Correct Answer
verified
Multiple Choice
A) discount rate that the firm should apply to all of the projects it undertakes.
B) rate of return a company must earn on its existing assets to maintain the current value of its stock.
C) coupon rate the firm should expect to pay on its next bond issue.
D) minimum discount rate the firm should require on any new project.
E) rate of return debtholders should expect to earn on their investment in this firm.
Correct Answer
verified
Multiple Choice
A) 13.12 percent
B) 13.74 percent
C) 12.63 percent
D) 12.77 percent
E) 13.01 percent
Correct Answer
verified
Multiple Choice
A) 4.28 percent
B) 4.22 percent
C) 4.35 percent
D) 4.93 percent
E) 4.41 percent
Correct Answer
verified
Multiple Choice
A) tends to remain static even as the company's level of risk increases.
B) increases as the unsystematic risk of the company's stock increases.
C) is affected by either a change in the company's beta or its projected rate of growth.
D) equals the risk-free rate plus the market risk premium.
E) equals the company's pretax weighted average cost of capital.
Correct Answer
verified
Multiple Choice
A) subjective risk
B) pure play
C) divisional cost of capital
D) capital adjustment
E) security market line
Correct Answer
verified
Multiple Choice
A) −$409
B) $618
C) −$308
D) $427
E) $573
Correct Answer
verified
Multiple Choice
A) 12.49 percent
B) 12.84 percent
C) 13.47 percent
D) 14.07 percent
E) 13.33 percent
Correct Answer
verified
Multiple Choice
A) $1.07
B) $2.11
C) $1.64
D) $1.73
E) $1.98
Correct Answer
verified
Multiple Choice
A) $411
B) $1,109
C) −$1,807
D) $938
E) −$2,399
Correct Answer
verified
Multiple Choice
A) $17,306,191
B) $15,022,949
C) $16,318,414
D) $15,719,310
E) $16,666,667
Correct Answer
verified
Multiple Choice
A) $612,652
B) $618,406
C) $686,005
D) $697,747
E) $656,636
Correct Answer
verified
Multiple Choice
A) accept all positive net present value projects.
B) increase the average risk level of the company over time.
C) reject all high-risk projects.
D) reject all negative net present value projects.
E) favor low-risk projects over high-risk projects.
Correct Answer
verified
Showing 81 - 99 of 99
Related Exams