Shortening activity durations is called


A) expediting.
B) crashing.
C) vendor management.
D) null nodes.
E) trade-off analysis.

F) A) and B)
G) B) and C)

Correct Answer

verifed

verified

Which phase of the project life cycle happens in conjunction with project execution?


A) initiating
B) planning
C) executing
D) monitoring and controlling
E) closing

F) A) and B)
G) C) and D)

Correct Answer

verifed

verified

The project management strategy of injecting additional resources in order to reduce the length of the project is called


A) expediting.
B) rushing.
C) panicking.
D) crashing.
E) loading.

F) B) and D)
G) C) and D)

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated expected (mean) time for project completion? A) 160 days B) 170 days C) 200 days D) 210 days E) 300 days What is the estimated expected (mean) time for project completion?


A) 160 days
B) 170 days
C) 200 days
D) 210 days
E) 300 days

F) A) and D)
G) C) and D)

Correct Answer

verifed

verified

The project computing algorithm requires both a forward and a backward pass.

A) True
B) False

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated slack time for activity W? A) 0 day B) 25 days C) 35 days D) 45 days E) 85 days What is the estimated slack time for activity W?


A) 0 day
B) 25 days
C) 35 days
D) 45 days
E) 85 days

F) A) and C)
G) A) and E)

Correct Answer

verifed

verified

Which of the following is not a form of risk reduction in project management?


A) backup system
B) outsourcing
C) risk sharing
D) scenario analysis
E) frequent monitoring of critical project dimensions in order to catch and eliminate problems early

F) A) and B)
G) D) and E)

Correct Answer

verifed

verified

There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2 days. The standard deviation of the critical path is


A) 3.
B) 5.
C) 9.
D) 16.
E) 25.

F) C) and E)
G) C) and D)

Correct Answer

verifed

verified

Consider the portion of a project depicted by this graph: Consider the portion of a project depicted by this graph:   What is the latest start time of activity 6-7 if the latest finish of activity 7-8 is 26, and the latest finish of activity 7-9 is 23? A) 18 B) 17 C) 13 D) 12 E) 10 What is the latest start time of activity 6-7 if the latest finish of activity 7-8 is 26, and the latest finish of activity 7-9 is 23?


A) 18
B) 17
C) 13
D) 12
E) 10

F) A) and B)
G) C) and E)

Correct Answer

verifed

verified

An advantage of Gantt charts in project management is that they identify which activities can be delayed without delaying the overall project.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is not typically treated as part of a project life cycle?


A) feasibility assessment
B) planning
C) maturity
D) release resources
E) project staffing

F) All of the above
G) B) and C)

Correct Answer

verifed

verified

The advantage a precedence diagram has over a Gantt chart is


A) its ability to reveal relationships among activities.
B) its difficulty in depicting networks.
C) its complexity.
D) its simplicity.
E) its lack of riskiness.

F) C) and E)
G) All of the above

Correct Answer

verifed

verified

A disadvantage of activity-on-node diagrams is the occasional need for dummy activities.

A) True
B) False

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the probability that the critical path for this project will be completed within 52 weeks? A) .1554 B) .3108 C) .3466 D) .6554 E) .8277 What is the probability that the critical path for this project will be completed within 52 weeks?


A) .1554
B) .3108
C) .3466
D) .6554
E) .8277

F) A) and D)
G) C) and D)

Correct Answer

verifed

verified

The sum of times of the longest path in a network indicates expected project duration, and the activities represent the critical activities.

A) True
B) False

Correct Answer

verifed

verified

To _____ an activity means to shorten the time it will take.


A) smash
B) fund
C) crash
D) aggregate
E) matrix

F) A) and C)
G) A) and E)

Correct Answer

verifed

verified

The earliest finish time for an activity is equal to the latest finish time minus the activity slack.

A) True
B) False

Correct Answer

verifed

verified

Project management differs from management of more traditional activities mainly because of: (I) its limited time frame.(II) its unique, defined set of activities.(III) the requirement for use of the appropriate resources.(IV) the need for planning and execution.


A) I
B) II
C) I and II
D) I and III
E) I, II, and IV

F) A) and C)
G) B) and E)

Correct Answer

verifed

verified

Which decision in project management has typical factors that include establishing appropriate metrics for evaluating the project and managing equipment?


A) deciding which projects to implement
B) selecting the project manager
C) selecting the project team
D) planning and designing the project
E) managing and controlling project resources

F) A) and E)
G) B) and D)

Correct Answer

verifed

verified

The costs associated with risk events tend to be lower near the beginning of a project and higher near the end of the project.

A) True
B) False

Correct Answer

verifed

verified