A) I and II
B) II and III
C) III only
D) I and III
E) I, II, and III
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) cost
B) schedule
C) resources
D) quality
E) performance objectives
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 22
B) 23
C) 24
D) 25
E) 26
Correct Answer
verified
Multiple Choice
A) estimating the likelihood of chance events occurring
B) planning to eliminate chance events
C) identifying potential chance events
D) formulating contingency plans for chance events
E) analyzing the consequences of chance events
Correct Answer
verified
Multiple Choice
A) essentially theoretical.
B) its features that make it attractive in practice.
C) its symmetry.
D) It is bimodal.
E) It can easily be converted to a normal distribution.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) the mean and variance of every activity
B) the mean and variance of activities on the critical path
C) the standard deviation of activities on the critical path
D) each activity's probability of completion
E) the distribution of activity times
Correct Answer
verified
Multiple Choice
A) 0.
B) 1.
C) 4.
D) 5.
E) 9.
Correct Answer
verified
Multiple Choice
A) They preserve the separate identities of activities.
B) They clarify precedence relationships among activities.
C) They have an activity time equal to zero.
D) They have an activity time variance equal to zero.
E) They are used in activities-on-nodes (AON) network diagrams.
Correct Answer
verified
Multiple Choice
A) 2.
B) 4.
C) 8.
D) 16.
E) 64.
Correct Answer
verified
Multiple Choice
A) .6826
B) .8413
C) .9544
D) .9772
E) .9987
Correct Answer
verified
Multiple Choice
A) paths that are not independent
B) networks with each activity on only one path
C) activity times that cannot be crashed
D) noncritical paths that have no variability
E) critical paths with activities with deterministic time estimates
Correct Answer
verified
Multiple Choice
A) 0.
B) 1.
C) 5.
D) 6.
E) 11.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 12.
B) 17.
C) 20.
D) 36.
E) 77.
Correct Answer
verified
Multiple Choice
A) initiating
B) planning
C) executing
D) monitoring and controlling
E) closing
Correct Answer
verified
True/False
Correct Answer
verified
Showing 81 - 100 of 118