The following matrix shows relative costs for various job-machine combinations. Assume there must be one-to-one matching between jobs and machines. Which set of pairs constitutes the minimum-cost solution using the assignment method? The following matrix shows relative costs for various job-machine combinations. Assume there must be one-to-one matching between jobs and machines. Which set of pairs constitutes the minimum-cost solution using the assignment method?   A) 1-B, 2-C, 3-A B) 1-B, 2-A, 3-C C) 1-A, 2-C, 3-B D) 1-A, 2-B, 3-C E) 1-C, 2-A, 3-B


A) 1-B, 2-C, 3-A
B) 1-B, 2-A, 3-C
C) 1-A, 2-C, 3-B
D) 1-A, 2-B, 3-C
E) 1-C, 2-A, 3-B

F) B) and C)
G) All of the above

Correct Answer

verifed

verified

The scheduling sequencing rule which always results in the lowest average completion (flow) time is the


A) first come, first served (FCFS) rule.
B) shortest processing time first (SPT) rule.
C) earliest due date first (EDD) rule.
D) least slack per operation first (S/O) rule.
E) run until slack happens (RUSH) rule.

F) B) and C)
G) A) and E)

Correct Answer

verifed

verified

The purpose of cyclical scheduling is to


A) eliminate weekends and holidays.
B) establish work assignments that will repeat on a cyclical basis.
C) add flexible hours.
D) incorporate overtime.
E) rotate schedules across a service workforce to ensure everyone gets an equal number of weekends off per year.

F) All of the above
G) A) and B)

Correct Answer

verifed

verified

When operations are often bottlenecked, additional planned idle time will improve the throughput in those areas.

A) True
B) False

Correct Answer

verifed

verified

Priority rules generally assume that job setup cost is independent of the processing sequence of jobs.

A) True
B) False

Correct Answer

verifed

verified

The priority rule which will sequence jobs in the order they are received is


A) EDD.
B) LIFO.
C) SPT.
D) CR.
E) FCFS.

F) C) and E)
G) A) and B)

Correct Answer

verifed

verified

For the jobs listed below, which processing sequence would result using Johnson's rule? For the jobs listed below, which processing sequence would result using Johnson's rule?   A) c-a-d-b B) b-d-a-c C) a-b-c-d D) d-c-b-a E) c-a-b-d


A) c-a-d-b
B) b-d-a-c
C) a-b-c-d
D) d-c-b-a
E) c-a-b-d

F) B) and E)
G) B) and D)

Correct Answer

verifed

verified

A schedule chart depicts the loading and idle times for a group of machines or departments.

A) True
B) False

Correct Answer

verifed

verified

Job X, which has a duration of four days, is due by the close of business on Friday, December 23. Without looking at the work already scheduled on X's required resource, the scheduler schedules X to be begun on the morning of Tuesday, December 20. This is an example of


A) infinite scheduling.
B) finite scheduling.
C) forward scheduling.
D) backward scheduling.
E) prioritization.

F) None of the above
G) B) and D)

Correct Answer

verifed

verified

Which costs depend on the order in which the jobs are processed?


A) sequencing
B) setup
C) finishing
D) transportation
E) distribution

F) C) and D)
G) A) and B)

Correct Answer

verifed

verified

Which of the following is not an example of a high-volume system?


A) aircraft manufacturing
B) magazine printing
C) petroleum refining
D) waste treatment
E) commercial donut baking

F) A) and D)
G) C) and D)

Correct Answer

verifed

verified

Scheduling pertains to


A) hiring workers.
B) process selection.
C) buying machinery.
D) timing the use of specific resources.
E) determining the lowest cost.

F) B) and D)
G) B) and C)

Correct Answer

verifed

verified

The operations manager of a body and paint shop has five cars to schedule for repair. He would like to minimize the makespan to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body and paint work on each are as follows: The operations manager of a body and paint shop has five cars to schedule for repair. He would like to minimize the makespan to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body and paint work on each are as follows:   Where in the optimum sequence should car E be scheduled? A) first B) second C) third D) fourth E) fifth Where in the optimum sequence should car E be scheduled?


A) first
B) second
C) third
D) fourth
E) fifth

F) A) and C)
G) C) and D)

Correct Answer

verifed

verified

Effective scheduling cannot


A) yield cost savings and improved productivity.
B) reduce the need for expansion of facilities.
C) improve customer service.
D) eliminate the need to train employees.
E) improve patient care in medical settings.

F) B) and C)
G) B) and D)

Correct Answer

verifed

verified

The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received: The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received:   If he uses the shortest processing time first priority rule to schedule these jobs, what will be the average number of jobs in his shop today? A) 0 B) 1 C) 2 D) 3 E) 4 If he uses the shortest processing time first priority rule to schedule these jobs, what will be the average number of jobs in his shop today?


A) 0
B) 1
C) 2
D) 3
E) 4

F) None of the above
G) B) and E)

Correct Answer

verifed

verified

_____ charts are often the preferred charts related to loading and scheduling activities.


A) Pareto
B) Mekko
C) Gantt
D) Histogram
E) Flow

F) B) and C)
G) A) and B)

Correct Answer

verifed

verified

Priority rules are used in low-volume systems to identify an optimal processing sequence.

A) True
B) False

Correct Answer

verifed

verified

Scheduling in intermediate-volume systems has three basic issues: run size, timing, and sequence.

A) True
B) False

Correct Answer

verifed

verified

In a task assignment situation, in how many different ways can five jobs be assigned to five machines if each job must be assigned to each machine and each machine must be assigned one job?


A) 1
B) 5
C) 25
D) 120
E) 3,125

F) B) and C)
G) B) and D)

Correct Answer

verifed

verified

The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received: The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received:   If he uses the first come, first served priority rule to schedule these jobs, what will be the average completion time? A) 7.5 hours B) 5 hours C) 3 hours D) 2.5 hours E) 2 hours If he uses the first come, first served priority rule to schedule these jobs, what will be the average completion time?


A) 7.5 hours
B) 5 hours
C) 3 hours
D) 2.5 hours
E) 2 hours

F) A) and B)
G) B) and E)

Correct Answer

verifed

verified