Under lot-for-lot, order sizes for component parts are essentially determined directly from which one of the following?


A) gross requirements
B) net requirements
C) economic order quantity
D) gross requirements minus scheduled receipts
E) net requirements minus projected on-hand inventory

F) A) and B)
G) A) and D)

Correct Answer

verifed

verified

The MRP input listing the assemblies, subassemblies, parts, and raw materials needed to produce one unit of finished product is the


A) master production schedule.
B) bill of materials.
C) inventory records.
D) assembly time chart.
E) net requirements chart.

F) B) and E)
G) None of the above

Correct Answer

verifed

verified

Lot-for-lot ordering in MRP provides coverage for some predetermined number of periods (such as two or three)that extend beyond the orders already received for those periods.

A) True
B) False

Correct Answer

verifed

verified

Which of the following most closely describes dependent demand?


A) demand generated by suppliers
B) estimates of demand using regression analysis of independent variables
C) derived demand
D) demands placed on suppliers by their customers
E) net material requirements

F) A) and C)
G) A) and E)

Correct Answer

verifed

verified

The master production schedule states which end items are to be produced, in addition to when and how many.

A) True
B) False

Correct Answer

verifed

verified

Lumpy demand for components results primarily from the periodic scheduling of batch production.

A) True
B) False

Correct Answer

verifed

verified

Bunny Helpers, Inc., has just received an order for 100 Deluxe Easter Baskets, which must be ready for delivery at the start of week 6. An MRP planner has prepared the following table showing product structure, lead times (orders are lot-for-lot) , and quantities on hand Bunny Helpers, Inc., has just received an order for 100 Deluxe Easter Baskets, which must be ready for delivery at the start of week 6. An MRP planner has prepared the following table showing product structure, lead times (orders are lot-for-lot) , and quantities on hand   Each Deluxe Basket contains two dark chocolate truffles and four carved chocolate eggs. How many dark chocolate eggs should be ordered? A) 310 B) 450 C) 500 D) 550 E) 600 Each Deluxe Basket contains two dark chocolate truffles and four carved chocolate eggs. How many dark chocolate eggs should be ordered?


A) 310
B) 450
C) 500
D) 550
E) 600

F) A) and C)
G) A) and B)

Correct Answer

verifed

verified

A visual depiction of the subassemblies and components that are needed to produce and/or assemble a product is called a(n)


A) assembly time chart.
B) product structure tree.
C) MRP II.
D) pegging.
E) Gantt chart.

F) A) and B)
G) C) and D)

Correct Answer

verifed

verified

Net requirements for component J are as follows: 60 units in week 2, 40 units in week 3, and 60 units in week 5. If a fixed-period, two-period lot-sizing method is used, what will be the quantity of the first planned receipt?


A) 60 units
B) 120 units
C) 180 units
D) cannot be determined
E) none of the choices

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

Which of the following is not usually necessary in order to have an effective MRP system?


A) a computer and software
B) an accurate bill of materials
C) lot-for-lot ordering
D) an up-to-date master schedule
E) integrity of file data

F) B) and D)
G) None of the above

Correct Answer

verifed

verified

MRP is used to answer what three questions?


A) What is needed? / Who is needed? / How much is needed?
B) Where it is needed? / When it is needed? / What is needed?
C) When is it needed? / How much is needed? / What is needed?
D) How much is needed? / Why it is needed? / When it is needed?
E) Why it is needed? / What is needed? / Where it is needed?

F) A) and B)
G) All of the above

Correct Answer

verifed

verified

ERP is now about enterprise applications


A) deployment.
B) development.
C) interfaces.
D) integration.
E) networking.

F) B) and E)
G) A) and E)

Correct Answer

verifed

verified

The bill of materials indicates how much material will be needed to produce the quantities on a given master production schedule.

A) True
B) False

Correct Answer

verifed

verified

The gross requirements at one level of an MRP plan determine the gross requirements at the next lower level continuing on down to the lowest levels shown on the bill of materials.

A) True
B) False

Correct Answer

verifed

verified

MRP II is simply an improved version of MRP that processes more quickly and can plan for a larger number of end items.

A) True
B) False

Correct Answer

verifed

verified

When MRP II systems include feedback to revise a plan that is not feasible, they are known as


A) MRP III.
B) enterprise resource planning.
C) circular MRP.
D) feasible MRP.
E) closed loop MRP.

F) A) and B)
G) A) and E)

Correct Answer

verifed

verified

Refer to this product tree Refer to this product tree   If 17 Ps are needed, and on-hand inventory consists of 10 As, 15 Bs, 20 Cs, 12 Ms, and 5 Ns, how many Cs are needed? A) 48 B) 144 C) 192 D) 212 E) 272 If 17 Ps are needed, and on-hand inventory consists of 10 As, 15 Bs, 20 Cs, 12 Ms, and 5 Ns, how many Cs are needed?


A) 48
B) 144
C) 192
D) 212
E) 272

F) B) and D)
G) A) and D)

Correct Answer

verifed

verified

Successful implementation of an effective MRP system depends upon: (1) the recognition of the difference between independent and dependent demand, and (2)


A) computers.
B) development of the EOQ model.
C) inventory control systems.
D) blanket purchase orders.
E) the Internet.

F) A) and B)
G) D) and E)

Correct Answer

verifed

verified

An MRP system whose records are updated continuously is referred to as a(n)


A) regenerative system.
B) batch-type system.
C) Plossl-Wright system.
D) net-change system.
E) gross-change system.

F) A) and E)
G) B) and D)

Correct Answer

verifed

verified

Independent demand tends to be more "lumpy" than dependent demand, meaning that we need large quantities followed by periods of no demand.

A) True
B) False

Correct Answer

verifed

verified

Showing 21 - 40 of 85