Correct Answer
verified
Multiple Choice
A) Capacity limits the rate of output possible.
B) Capacity affects operating costs.
C) Capacity is a major determinant of initial costs.
D) Capacity is a long-term commitment of resources.
E) Capacity chunks can be added or deleted quickly and inexpensively.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 80 percent
B) 72 percent
C) 90 percent
D) 70 percent
E) 60 percent
Correct Answer
verified
Multiple Choice
A) 5,000
B) 3,000
C) 2,000
D) 1,000
E) 0
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 5,000
B) 8,000
C) 2,000
D) 4,000
E) 6,000
Correct Answer
verified
Multiple Choice
A) $0
B) $9,000
C) $15,000
D) $10,000
E) $30,000
Correct Answer
verified
Multiple Choice
A) capacity cushion
B) first station
C) bottleneck
D) economy of scale
E) diseconomy of scale
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) actual output to effective capacity.
B) actual output to design capacity.
C) design capacity to effective capacity.
D) effective capacity to actual output.
E) design capacity to actual output.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) improve
B) support
C) identify
D) elevate
E) modify
Correct Answer
verified
Multiple Choice
A) payback.
B) net present value.
C) internal rate of return.
D) queuing.
E) cost-volume.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The discount rate must be adjusted to account for inflation.
B) Some cash flows are positive and other cash flows are negative.
C) The payback period might not be long enough to justify a capacity decision.
D) Capacity decisions are made amidst much uncertainty, so cash flows cannot be estimated with great accuracy.
E) There is a cash outflow at the outset followed by, possibly, net cash inflows.
Correct Answer
verified
Multiple Choice
A) lead time flexibility strategy.
B) expand-early strategy.
C) go-with-the-flow strategy.
D) backordering.
E) delayed differentiation.
Correct Answer
verified
Multiple Choice
A) 100
B) 2,000.00
C) 500
D) 1,000.00
E) 800
Correct Answer
verified
Multiple Choice
A) output equals capacity.
B) total cost equals total revenue.
C) total cost equals profit.
D) variable cost equals fixed cost.
E) variable cost equals total revenue.
Correct Answer
verified
Showing 1 - 20 of 85
Related Exams