Filters
Question type

Study Flashcards

Net requirements for component J are as follows: 60 units in week 2, 40 units in week 3, and 60 units in week 5. If a fixed-period, two-period lot-sizing method is used, what will be the quantity of the first planned receipt?


A) 60 units
B) 120 units
C) 180 units
D) cannot be determined
E) none of the choices

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Refer to this product tree: Refer to this product tree:   If 17 Ps are needed, and on-hand inventory consists of 10 As, 15 Bs, 20 Cs, 12 Ms, and 5 Ns, how many Cs are needed? A)  48 B)  144 C)  192 D)  212 E)  272 If 17 Ps are needed, and on-hand inventory consists of 10 As, 15 Bs, 20 Cs, 12 Ms, and 5 Ns, how many Cs are needed?


A) 48
B) 144
C) 192
D) 212
E) 272

F) B) and C)
G) B) and E)

Correct Answer

verifed

verified

The MRP input stating which end items are to be produced, when they are needed, and what quantities are needed, is the:


A) master schedulE.
B) bill of materials.
C) inventory records.
D) assembly time chart.
E) net requirements chart.

F) C) and D)
G) A) and D)

Correct Answer

verifed

verified

Refer to this product tree: Refer to this product tree:   If 17 Ps are needed, and no on-hand inventory exists for any items, how many Cs will be needed? A)  8 B)  16 C)  136 D)  204 E)  272 If 17 Ps are needed, and no on-hand inventory exists for any items, how many Cs will be needed?


A) 8
B) 16
C) 136
D) 204
E) 272

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

A visual depiction of the subassemblies and components that are needed to produce and/or assemble a product is called a(n) :


A) assembly time chart.
B) product structure treE.
C) MRP II.
D) pegging.
E) Gantt chart.

F) A) and C)
G) A) and B)

Correct Answer

verifed

verified

The master schedule needs to be for a period long enough to cover the stacked or cumulative lead time necessary to produce the end items.

A) True
B) False

Correct Answer

verifed

verified

In a master schedule, the planning horizon is often separated into a series of time periods called:


A) pegging.
B) lead times.
C) stacked lead times.
D) time buckets.
E) firm, fixed, and frozen.

F) A) and C)
G) C) and D)

Correct Answer

verifed

verified

Lot-for-lot ordering in MRP provides coverage for some predetermined number of periods (such as two or three) that extend beyond the orders already received for those periods.

A) True
B) False

Correct Answer

verifed

verified

Capacity requirements planning helps managers reconcile __________ with __________.


A) what is needed; what has been done
B) what is needed; what is possible
C) what has been done; who will be doing it
D) what needs to be done; where it will be done
E) what has been done; how much what needs to be done will cost

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

The _________ of ERP makes it valuable as a strategic planning tool.


A) Internet base
B) rapid batch capability
C) employee focus
D) real-time aspect
E) database structure

F) None of the above
G) A) and B)

Correct Answer

verifed

verified

The MRP input listing the assemblies, subassemblies, parts, and raw materials needed to produce one unit of finished product is the:


A) master production schedule.
B) bill of materials.
C) inventory records.
D) assembly time chart.
E) net requirements chart.

F) D) and E)
G) A) and C)

Correct Answer

verifed

verified

MRP output reports are divided into two main groups, daily and weekly.

A) True
B) False

Correct Answer

verifed

verified

An assembly-time chart indicates gross and net requirements taking into account the current available inventory.

A) True
B) False

Correct Answer

verifed

verified

Which one of the following most closely describes the MRP approach that is used for components or subassemblies to compensate for variations in lead time?


A) pegging
B) safety stock
C) increased order sizes
D) safety time
E) low-level coding

F) None of the above
G) C) and E)

Correct Answer

verifed

verified

MRP works best if the inventory items have dependent demand.

A) True
B) False

Correct Answer

verifed

verified

In MRP, the gross requirements of a given component part are calculated directly from:


A) net requirements + projected on-hand inventory.
B) gross requirements of the immediate parent.
C) planned order releases of the end item.
D) net requirements of the end item.
E) planned order releases of the immediate parent.

F) A) and B)
G) B) and C)

Correct Answer

verifed

verified

Which of the following represents an attempt to balance the benefits of stability in the production plan against the benefits of responding quickly to new orders?


A) safety stock
B) safety time
C) bills of material
D) time fences
E) fixed-period lot sizing

F) D) and E)
G) C) and E)

Correct Answer

verifed

verified

Which of these items would be most likely to have dependent demand?


A) computer chips
B) potato chips
C) poker chips
D) chocolate chip cookies
E) wood chippers

F) B) and C)
G) D) and E)

Correct Answer

verifed

verified

The output of MRP is:


A) gross requirements.
B) net requirements.
C) a schedule of planned orders for all parts and end items.
D) inventory reorder points.
E) economic order quantities and reorder points.

F) A) and C)
G) A) and B)

Correct Answer

verifed

verified

Safety time is sometimes used in MRP rather than safety stock quantities.

A) True
B) False

Correct Answer

verifed

verified

Showing 61 - 80 of 81

Related Exams

Show Answer