Filters
Question type

Study Flashcards

Fast and simple are two common threads that run through the four building blocks of lean operations.

A) True
B) False

Correct Answer

verifed

verified

Lean purchasing requires frequent contract bidding by multiple sources to ensure the buyer of competitive prices.

A) True
B) False

Correct Answer

verifed

verified

Lean systems typically require that suppliers be able to provide large lots at periodic intervals.

A) True
B) False

Correct Answer

verifed

verified

The four building blocks of lean operations are: product design, process design, personnel/organizational elements, and manufacturing planning and control.

A) True
B) False

Correct Answer

verifed

verified

The lean philosophy recognizes that some work-in-process inventories are a necessary investment to allow for smooth work flow.

A) True
B) False

Correct Answer

verifed

verified

The goals of both kanban and MRP include:


A) smooth rates of output.
B) reduction of inventories.
C) explosion of materials required.
D) determination of capacity required.
E) larger lot sizes.

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

Limited WIP lowers inventory carrying costs but reduces flexibility.

A) True
B) False

Correct Answer

verifed

verified

Engineering changes should not be made in the six-month period following the introduction of a new product.

A) True
B) False

Correct Answer

verifed

verified

Having a vendor be responsible for managing the restocking of inventory is what is meant by the term:


A) JIT II.
B) MRP II.
C) SCM I.
D) EOQ III.
E) POQ II.

F) D) and E)
G) A) and E)

Correct Answer

verifed

verified

One problem with lean operations is that they can lead to much stress on workers due to their increased responsibility for process and quality improvement.

A) True
B) False

Correct Answer

verifed

verified

One major difference between the use of kanban and MRP in scheduling the items to be produced or ordered is that kanban is primarily a manual system while MRP uses computers.

A) True
B) False

Correct Answer

verifed

verified

The ultimate goal in a lean system is:


A) low to moderate levels of inventory.
B) high quality, zero defects.
C) minimal waste (less than 6 percent) .
D) balanced and rapid flow.
E) all of these.

F) A) and B)
G) A) and E)

Correct Answer

verifed

verified

A fundamental tenet of the lean philosophy is that workers are paid based on seniority.

A) True
B) False

Correct Answer

verifed

verified

Increased setup times generally require increased work-in-process inventories.

A) True
B) False

Correct Answer

verifed

verified

Process design that supports lean does not include:


A) production flexibility.
B) duplicate facilities.
C) setup time reduction.
D) minimal inventory storage.
E) small lot sizes.

F) B) and E)
G) B) and D)

Correct Answer

verifed

verified

In a pull system, the accumulation of excessive inventory in front of a workstation is avoided even if there are problems such as equipment failure at that workstation which prevent it from completing its work.

A) True
B) False

Correct Answer

verifed

verified

The small lot-sizing policy works well in a situation where both holding costs and setup costs are high.

A) True
B) False

Correct Answer

verifed

verified

The term that refers to the automatic detection of defects is:


A) kaizen.
B) kanban.
C) autonomation.
D) automation.
E) 100 percent inspection.

F) B) and C)
G) A) and B)

Correct Answer

verifed

verified

In a lean environment, anything not essential to the product or process is viewed as waste.

A) True
B) False

Correct Answer

verifed

verified

Although transitioning to a lean system can be a powerful means of improving performance, some believe that using __________ along with lean can lead to even better results.


A) kaizen
B) EOQ
C) Six Sigma
D) JIT
E) Jidoka

F) A) and E)
G) A) and B)

Correct Answer

verifed

verified

Showing 41 - 60 of 79

Related Exams

Show Answer