The following table contains information about five jobs waiting to be processed at work center number three.  Job  Processing Time  (hrs)   Hours Until Due  a 1415 b 1020 c 1818 d 216 e 421\begin{array} { c c c } \hline \text { Job } & \begin{array} { r } \text { Processing Time } \\\text { (hrs) }\end{array} & \text { Hours Until Due } \\\text { a } & 14 & 15 \\\text { b } & 10 & 20 \\\text { c } & 18 & 18 \\\text { d } & 2 & 16 \\\text { e } & 4 & 21\end{array} The sequence that would result using the SPT rule is:


A) e-b-c-d-a.
B) c-a-b-e-d.
C) a-d-c-e-b.
D) d-e-b-a-C.
E) e-d-b-a-c.

F) A) and E)
G) A) and B)

Correct Answer

verifed

verified

The Hungarian method is limited to a maximum of two jobs per resource.

A) True
B) False

Correct Answer

verifed

verified

A major difference between manufacturing and service systems in terms of scheduling is:


A) variability in arrival and service rates.
B) processing cost per unit.
C) the number of units to be processed.
D) length of processing time.
E) output rate.

F) D) and E)
G) B) and C)

Correct Answer

verifed

verified

The theory of constraints has a goal of maximizing flow through the entire system.

A) True
B) False

Correct Answer

verifed

verified

Organizations with fixed, perishable capacity can benefit from:


A) yield management.
B) price increases.
C) constraints.
D) suboptimization.
E) waiting lines.

F) B) and D)
G) A) and E)

Correct Answer

verifed

verified

The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants-Charlie, Betty, Johnny, and Rick-to complete any of the four projects, as follows: The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants-Charlie, Betty, Johnny, and Rick-to complete any of the four projects, as follows:   Assume there must be one-to-one matching between consultants and projects. In how many different ways can she assign these consultants to these projects? A)  4 B)  8 C)  16 D)  24 E)  256 Assume there must be one-to-one matching between consultants and projects. In how many different ways can she assign these consultants to these projects?


A) 4
B) 8
C) 16
D) 24
E) 256

F) B) and D)
G) A) and E)

Correct Answer

verifed

verified

There are four resources and four jobs to be done. Assume there must be one-to-one matching between jobs and resources. The time required for each resource to do each job is as follows:  Job (Hours)   Resource  A  B  C  D 15877249593698747669\begin{array} { c c c c c } & { \text { Job (Hours) } } \\\text { Resource } & \text { A } & \text { B } & \text { C } & \text { D } \\1 & 5 & 8 & 7 & 7 \\2 & 4 & 9 & 5 & 9 \\3 & 6 & 9 & 8 & 7 \\4 & 7 & 6 & 6 & 9\end{array} After the row and column reductions, what is the resulting entry in the new table for assigning resource 4 to job D?


A) 0 hours
B) 2 hours
C) 3 hours
D) 6 hours
E) 9 hours

F) A) and B)
G) C) and E)

Correct Answer

verifed

verified

Which of the following is not a measure for judging the effectiveness of a schedule sequence?


A) average number of jobs at the work center
B) total number of jobs at the work center
C) average completion (flow) time
D) average job tardiness
E) length of time between start of first job to completion of the last job in the work center

F) None of the above
G) A) and E)

Correct Answer

verifed

verified

There are four resources and four jobs to be done. Assume there must be one-to-one matching between jobs and resources. The time required for each resource to do each job is as follows:  Job (Hours)   Resource  A  B  C  D 15877249593698747669\begin{array} { c c c c c } & { \text { Job (Hours) } } \\\text { Resource } & \text { A } & \text { B } & \text { C } & \text { D } \\1 & 5 & 8 & 7 & 7 \\2 & 4 & 9 & 5 & 9 \\3 & 6 & 9 & 8 & 7 \\4 & 7 & 6 & 6 & 9\end{array} After the row reduction, what is the resulting entry in the new table for assigning resource 4 to Job D?


A) 0 hours
B) 2 hours
C) 3 hours
D) 6 hours
E) 9 hours

F) B) and C)
G) C) and E)

Correct Answer

verifed

verified

Which of the following is not an assumption of priority rules?


A) The set of jobs is known: no new jobs arrive after processing begins.
B) Setup time is independent of processing sequence.
C) Finite loading is assumeD.
D) Processing times are deterministic.
E) No machine breakdowns are assumed.

F) All of the above
G) C) and D)

Correct Answer

verifed

verified

The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants-Charlie, Betty, Johnny, and Rick-to complete any of the four projects, as follows: The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants-Charlie, Betty, Johnny, and Rick-to complete any of the four projects, as follows:   Assume there must be one-to-one matching between consultants and projects. For the optimal schedule, what is the total number of hours it will take these consultants to complete these projects? A)  53 hours B)  46 hours C)  50 hours D)  61 hours E)  54 hours Assume there must be one-to-one matching between consultants and projects. For the optimal schedule, what is the total number of hours it will take these consultants to complete these projects?


A) 53 hours
B) 46 hours
C) 50 hours
D) 61 hours
E) 54 hours

F) A) and B)
G) B) and D)

Correct Answer

verifed

verified

Based on the cost information given in the following table, which set of job-machine pairs reflects the minimum-cost solution using the Assignment method? Based on the cost information given in the following table, which set of job-machine pairs reflects the minimum-cost solution using the Assignment method?   A)  1-B, 2-A, 3-C B)  1-A, 2-B, 3-C C)  1-C, 2-A, 3-B D)  1-B, 2-C, 3-A E)  1-C, 2-B, 3-A


A) 1-B, 2-A, 3-C
B) 1-A, 2-B, 3-C
C) 1-C, 2-A, 3-B
D) 1-B, 2-C, 3-A
E) 1-C, 2-B, 3-A

F) B) and E)
G) D) and E)

Correct Answer

verifed

verified

In theory of constraints scheduling, the __________ refers to the schedule and the __________ refers to inventory used to ensure that the bottleneck is never idle.


A) rope; drum
B) drum; rope
C) drum; buffer
D) buffer; drum
E) buffer; rope

F) All of the above
G) A) and D)

Correct Answer

verifed

verified

Scheduling in intermediate-volume systems has three basic issues: run size, timing, and sequence.

A) True
B) False

Correct Answer

verifed

verified

The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants-Charlie, Betty, Johnny, and Rick-to complete any of the four projects, as follows: The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants-Charlie, Betty, Johnny, and Rick-to complete any of the four projects, as follows:   Assume there must be one-to-one matching between consultants and projects. After the row and column reductions, what is the resulting entry in the new table for assigning Rick to project D? A)  0 hours B)  8 hours C)  10 hours D)  9 hours E)  22 hours Assume there must be one-to-one matching between consultants and projects. After the row and column reductions, what is the resulting entry in the new table for assigning Rick to project D?


A) 0 hours
B) 8 hours
C) 10 hours
D) 9 hours
E) 22 hours

F) B) and C)
G) C) and E)

Correct Answer

verifed

verified

A schedule chart depicts the loading and idle times for a group of machines or departments.

A) True
B) False

Correct Answer

verifed

verified

The operations manager of a body and paint shop has five cars to schedule for repair. He would like to minimize the makespan to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body and paint work on each are as follows:  Car  Body Work  (hrs)   Paint  (hrs)   A 102 B 54 C 75 D 36 E 17\begin{array} { c c c } \text { Car } & \begin{array} { c } \text { Body Work } \\\text { (hrs) }\end{array} & \begin{array} { c } \text { Paint } \\\text { (hrs) }\end{array} \\\text { A } & 10 & 2 \\\text { B } & 5 & 4 \\\text { C } & 7 & 5 \\\text { D } & 3 & 6 \\\text { E } & 1 & 7\end{array} Where in the optimum sequence should car E be scheduled?


A) first
B) second
C) third
D) fourth
E) fifth

F) A) and E)
G) A) and D)

Correct Answer

verifed

verified

In theory of constraints scheduling, the synchronization of the sequence of operations is referred to as the:


A) buffer.
B) bottleneck.
C) constraint.
D) ropE.
E) drum.

F) A) and B)
G) B) and E)

Correct Answer

verifed

verified

A scheduling rule used for sequencing jobs through two work centers such that makespan is minimized is:


A) critical ratio rule.
B) Johnson's rulE.
C) slack per operation rule.
D) shortest processing time rule.
E) Pareto rule.

F) A) and E)
G) A) and D)

Correct Answer

verifed

verified

Primary considerations in scheduling high-volume systems involve:


A) I and III
B) I and II
C) II and III
D) I, II, and III
E) II only

F) A) and E)
G) None of the above

Correct Answer

verifed

verified