Activity J has a duration of 7 and an earliest finish time of 21. If J's latest start time is 16, this must mean that J's slack is:


A) 7.
B) 4.
C) 3.
D) 2.
E) 1.

F) B) and D)
G) A) and D)

Correct Answer

verifed

verified

The probability that the project will go beyond the desired time is equal to one minus the joint probability that all paths will be completed within the desired time.

A) True
B) False

Correct Answer

verifed

verified

Consider the portion of a project depicted by this graph: Consider the portion of a project depicted by this graph:   What is the earliest finish time for activity 10-11 (far right-hand side)  if the earliest start time of 8-10 (upper left-hand side)  is 12 and the earliest start time of 9-10 (lower left-hand side)  is 13? A)  22 B)  23 C)  24 D)  25 E)  26 What is the earliest finish time for activity 10-11 (far right-hand side) if the earliest start time of 8-10 (upper left-hand side) is 12 and the earliest start time of 9-10 (lower left-hand side) is 13?


A) 22
B) 23
C) 24
D) 25
E) 26

F) A) and B)
G) A) and D)

Correct Answer

verifed

verified

The basis for use of the beta distribution in PERT is:


A) essentially theoretical.
B) its features that make it attractive in practicE.
C) its symmetry.
D) It is bimodal.
E) It can easily be converted to a normal distribution.

F) C) and D)
G) A) and B)

Correct Answer

verifed

verified

Which of the following would probably not involve the use of PERT?


A) planning and constructing a new city hall
B) developing an advertising campaign for a new product
C) designing and constructing a subway system
D) writing a poem
E) preparing for the visit of a foreign dignitary

F) A) and C)
G) All of the above

Correct Answer

verifed

verified

Which of the following is not a limitation of PERT and similar project-scheduling techniques?


A) They force the manager to organize and quantify information.
B) One or more important activities may be omitted from the network.
C) Precedence relationships may not all be correct as shown.
D) Time estimates may contain a "fudge factor."
E) The use of a computer is essential for large projects.

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

The task of identifying risks should involve everyone associated with the project.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is not true about the use of dummy activities in project networking?


A) They preserve the separate identities of activities.
B) They clarify precedence relationships among activities.
C) They have an activity time equal to zero.
D) They have an activity time variance equal to zero.
E) They are used in activities-on-nodes (AON) network diagrams.

F) A) and B)
G) B) and E)

Correct Answer

verifed

verified

Once a project is underway, the project manager usually is not responsible for effectively managing:


A) the people.
B) costs.
C) resources.
D) time.
E) project priority.

F) A) and B)
G) B) and C)

Correct Answer

verifed

verified

To _____ an activity means to shorten the time it will take.


A) smash
B) fund
C) crash
D) aggregate
E) matrix

F) B) and D)
G) A) and E)

Correct Answer

verifed

verified

Which of the following is not characteristic of good risk management?


A) estimating the likelihood of chance events occurring
B) planning to eliminate chance events
C) identifying potential chance events
D) formulating contingency plans for chance events
E) analyzing the consequences of chance events

F) C) and E)
G) B) and E)

Correct Answer

verifed

verified

Most likely time generally is at least as long as optimistic time.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is not typically treated as part of a project life cycle?


A) feasibility assessment
B) planning
C) maturity
D) release resources
E) project staffing

F) C) and E)
G) A) and B)

Correct Answer

verifed

verified

A project is represented by the following diagram: A project is represented by the following diagram:   The expected duration of this project is: A)  12. B)  17. C)  20. D)  36. E)  77. The expected duration of this project is:


A) 12.
B) 17.
C) 20.
D) 36.
E) 77.

F) A) and E)
G) A) and C)

Correct Answer

verifed

verified

When developing probabilistic estimates of project duration, it is necessary to know which of the following?


A) the mean and variance of every activity
B) the mean and variance of activities on the critical path
C) the standard deviation of activities on the critical path
D) each activity's probability of completion
E) the distribution of activity times

F) All of the above
G) B) and C)

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the probability that this project will be completed within 130 days? A)  .8413 B)  .90 C)  .9544 D)  .9772 E)  .9987 What is the probability that this project will be completed within 130 days?


A) .8413
B) .90
C) .9544
D) .9772
E) .9987

F) B) and D)
G) None of the above

Correct Answer

verifed

verified

An advantage of Gantt charts in project management is that they identify which activities can be delayed without delaying the overall project.

A) True
B) False

Correct Answer

verifed

verified

The higher the node number, the longer the activity will take.

A) True
B) False

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated expected (mean)  time for project completion? A)  160 days B)  170 days C)  200 days D)  210 days E)  300 days What is the estimated expected (mean) time for project completion?


A) 160 days
B) 170 days
C) 200 days
D) 210 days
E) 300 days

F) B) and E)
G) C) and D)

Correct Answer

verifed

verified

Slack time is equal to LS-ES or LF-EF.

A) True
B) False

Correct Answer

verifed

verified