A) 7.
B) 4.
C) 3.
D) 2.
E) 1.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 22
B) 23
C) 24
D) 25
E) 26
Correct Answer
verified
Multiple Choice
A) essentially theoretical.
B) its features that make it attractive in practicE.
C) its symmetry.
D) It is bimodal.
E) It can easily be converted to a normal distribution.
Correct Answer
verified
Multiple Choice
A) planning and constructing a new city hall
B) developing an advertising campaign for a new product
C) designing and constructing a subway system
D) writing a poem
E) preparing for the visit of a foreign dignitary
Correct Answer
verified
Multiple Choice
A) They force the manager to organize and quantify information.
B) One or more important activities may be omitted from the network.
C) Precedence relationships may not all be correct as shown.
D) Time estimates may contain a "fudge factor."
E) The use of a computer is essential for large projects.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) They preserve the separate identities of activities.
B) They clarify precedence relationships among activities.
C) They have an activity time equal to zero.
D) They have an activity time variance equal to zero.
E) They are used in activities-on-nodes (AON) network diagrams.
Correct Answer
verified
Multiple Choice
A) the people.
B) costs.
C) resources.
D) time.
E) project priority.
Correct Answer
verified
Multiple Choice
A) smash
B) fund
C) crash
D) aggregate
E) matrix
Correct Answer
verified
Multiple Choice
A) estimating the likelihood of chance events occurring
B) planning to eliminate chance events
C) identifying potential chance events
D) formulating contingency plans for chance events
E) analyzing the consequences of chance events
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) feasibility assessment
B) planning
C) maturity
D) release resources
E) project staffing
Correct Answer
verified
Multiple Choice
A) 12.
B) 17.
C) 20.
D) 36.
E) 77.
Correct Answer
verified
Multiple Choice
A) the mean and variance of every activity
B) the mean and variance of activities on the critical path
C) the standard deviation of activities on the critical path
D) each activity's probability of completion
E) the distribution of activity times
Correct Answer
verified
Multiple Choice
A) .8413
B) .90
C) .9544
D) .9772
E) .9987
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 160 days
B) 170 days
C) 200 days
D) 210 days
E) 300 days
Correct Answer
verified
True/False
Correct Answer
verified
Showing 21 - 40 of 113
Related Exams