Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated slack time for activity D? A)  0 days B)  19 days C)  20 days D)  79 days E)  80 days What is the estimated slack time for activity D?


A) 0 days
B) 19 days
C) 20 days
D) 79 days
E) 80 days

F) A) and D)
G) B) and E)

Correct Answer

verifed

verified

One way that project management differs from management of more traditional activities is because of the limited time framework of projects.

A) True
B) False

Correct Answer

verifed

verified

Some organizations use a matrix organization to integrate the activities of specialists within a functional framework.

A) True
B) False

Correct Answer

verifed

verified

In the execution phase of a project's life cycle, activities are guided by decisions that were made in the __________ phase.


A) initiating
B) planning
C) monitoring/controlling
D) closing
E) assessment

F) A) and C)
G) A) and B)

Correct Answer

verifed

verified

The path in a network with the average length of time to completion is called the critical path.

A) True
B) False

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the probability that this project will be completed within 205 days? A)  0.6826 B)  0.8413 C)  0.9544 D)  0.9772 E)  0.9987 What is the probability that this project will be completed within 205 days?


A) 0.6826
B) 0.8413
C) 0.9544
D) 0.9772
E) 0.9987

F) A) and D)
G) B) and E)

Correct Answer

verifed

verified

If the expected length of a path is more than 2.5 standard deviations less than a desired project completion time, the path will not be a factor in assessing the probability of finishing the project on time.

A) True
B) False

Correct Answer

verifed

verified

Activity 4-5 in a network diagram has an optimistic time estimate of five days, a most likely time estimate of seven days, and a pessimistic time estimate of 10 days. Its expected time (in days) is approximately:


A) 5.
B) 6.
C) 7.
D) 8.
E) 9.

F) A) and D)
G) C) and D)

Correct Answer

verifed

verified

Many activities have slack time; if we add these slack times together, this represents the potential improvement in early completion for the project.

A) True
B) False

Correct Answer

verifed

verified

Which of the following leads to simulation being a useful tool with uncertain activity times?


A) paths that are not independent
B) networks with each activity on only one path
C) activity times that cannot be crashed
D) noncritical paths that have no variability
E) critical paths with activities with deterministic time estimates

F) C) and D)
G) B) and D)

Correct Answer

verifed

verified

There are four activities on the critical path. Coincidentally, their standard deviations are all equal to 4. The standard deviation of the critical path is therefore equal to:


A) 2.
B) 4.
C) 8.
D) 16.
E) 64.

F) A) and E)
G) C) and D)

Correct Answer

verifed

verified

The earliest finish time for an activity is equal to the latest finish time minus the activity time.

A) True
B) False

Correct Answer

verifed

verified

Project management differs from management of more traditional activities mainly because of: (I) its limited time frame. (II) its unique, defined set of activities. (III) the requirement for use of the appropriate resources. (IV) the need for planning and execution.


A) I
B) II
C) I and II
D) I and III
E) I, II, and IV

F) B) and E)
G) A) and D)

Correct Answer

verifed

verified

Activity 7-8 is directly preceded by two activities-activity 5-7 and activity 6-7. Activity 5-7 has an expected time of five and an ES time of six. Activity 6-7 has an expected time of seven and an ES time of seven. Activity 7-8 has an expected time of 10. The ES for activity 7-8 is:


A) 11.
B) 14.
C) 21.
D) 24.
E) 25.

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Project management software eliminates constraint violations when there are shared resources.

A) True
B) False

Correct Answer

verifed

verified

If two consecutive activities on the same path each have two days of activity slack, this means that each of them can be delayed by two days without delaying the project.

A) True
B) False

Correct Answer

verifed

verified

Once a project is approved and underway, project managers are only responsible for effectively managing time and costs which, if done well, will assure project completion on time and on budget.

A) True
B) False

Correct Answer

verifed

verified

Project risk events tend to be unlikely __________ a project, but that's also when they tend to be the __________.


A) early in; most costly
B) late in; least costly
C) late in; most costly
D) before the beginning of; most complex
E) at the conclusion of; least complex

F) D) and E)
G) A) and D)

Correct Answer

verifed

verified

A hierarchical listing of what must be done in a project is called a:


A) work breakdown structure (WBS) .
B) PERT.
C) planning matrix.
D) crashing plan.
E) critical path.

F) B) and C)
G) A) and B)

Correct Answer

verifed

verified

Suppose a project is subject to the following risk events (each with a given probability of occurring and a cost associated with that occurrence) :  Event  Probability  Cost($000s)   I .253 II .654 III .112 IV 321\begin{array} { l c c } \text { Event } & \text { Probability } & \text { Cost(\$000s) } \\\text { I } & .2 & 53 \\\text { II } & .6 & 54 \\\text { III } & .1 & 12 \\\text { IV } & 3 & 21\end{array} Given these, Event _____ should probably get the most attention and Event _____ should probably get the least.


A) II; IV
B) III; IV
C) I; III
D) I; II
E) II; III

F) A) and C)
G) None of the above

Correct Answer

verifed

verified