A) The path from resource to task that passes through all critical components of a project plan
B) The path between tasks to the projects finish that passes through all critical components of a project plan
C) The path from start to finish that passes through all the tasks that are critical to completing the project in the shortest amount of time
D) The path from start to finish that passes through all the tasks that are critical to completing the project in the longest amount of time
Correct Answer
verified
Multiple Choice
A) Delivered on time
B) Delivered within budget
C) Meets the business's requirements
D) All of the above
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Short Answer
Correct Answer
verified
Multiple Choice
A) Specific, metrics, agreed upon, real, time valued
B) Specific, measurable, agreed upon, realistic, time framed
C) Specific, measurable, accurate, real, time valued
D) Specific, metrics, agreed upon, realistic, time framed
Correct Answer
verified
Short Answer
Correct Answer
verified
Multiple Choice
A) Specific factors that can limit options
B) Factors that are considered to be true, real, or certain without proof or demonstration
C) Quantifiable criteria that must be met for the project to be considered a success
D) A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities
Correct Answer
verified
Multiple Choice
A) Categorize projects
B) Perform a financial analysis
C) Focus on organizational goals
D) Develop a project plan
Correct Answer
verified
Short Answer
Correct Answer
verified
Multiple Choice
A) The application of knowledge, skills, tools, and techniques to project activities in order to meet or exceed stakeholder needs and expectations from a project
B) Any measurable, tangible, verifiable outcome, result, or item that is produced to complete a project or part of a project
C) Represent key dates when a certain group of activities must be performed
D) An individual who is an expert in project planning and management
Correct Answer
verified
Multiple Choice
A) Gantt chart
B) PERT chart
C) Dependency
D) All of the above
Correct Answer
verified
Multiple Choice
A) Prepared by the project manager
B) Easy to read
C) Appropriate to the project's size
D) Communicated to all key participants
Correct Answer
verified
Multiple Choice
A) Project manager
B) Project stakeholders
C) Executive sponsor
D) All of the above
Correct Answer
verified
Multiple Choice
A) Project manager
B) Project stakeholders
C) Executive sponsor
D) All of the above
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Short Answer
Correct Answer
verified
Multiple Choice
A) Specific factors that can limit options
B) Factors that are considered to be true, real, or certain without proof or demonstration
C) Quantifiable criteria that must be met for the project to be considered a success
D) A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities
Correct Answer
verified
True/False
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) Justification of the project
B) Definition of the project
C) Analysis of project risks
D) Expected results of the project
Correct Answer
verified