What is the estimated expected (mean) time for activity Y?


A) 30 days
B) 29 days
C) 38 days
D) 26 days
E) 35 days

F) A) and D)
G) B) and D)

Correct Answer

verifed

verified

Only activities on the critical path are initial candidates for crashing.

A) True
B) False

Correct Answer

verifed

verified

A disadvantage of activity-on-node diagrams is the occasional need for dummy activities.

A) True
B) False

Correct Answer

verifed

verified

Activity J has a duration of 7 and an earliest finish time of 21.If J's latest start time is 16, this must mean that J's slack is ________.


A) 7
B) 4
C) 3
D) 2
E) 1

F) None of the above
G) A) and D)

Correct Answer

verifed

verified

D

What is the estimated expected (mean) time (in weeks) for project completion?

Correct Answer

verifed

verified

Within what amount of time (in weeks) is there a 90% probability that the critical path for this project will be completed? 95%? 99%?

Correct Answer

verifed

verified

Although PERT and CPM were originally developed for somewhat different types of projects, they are now nearly identical in terms of analysis and procedures.

A) True
B) False

Correct Answer

verifed

verified

The basis for use of the beta distribution in PERT is:


A) essentially theoretical.
B) its adaptability.
C) its symmetry.
D) It is bimodal.
E) It can easily be converted to a normal distribution.

F) B) and D)
G) C) and D)

Correct Answer

verifed

verified

Matrix organizations transfer control of workers to project managers for the duration of the project.

A) True
B) False

Correct Answer

verifed

verified

What is the probability that the critical path for this project will be completed within 210 days?


A) 0.5000
B) 0.8413
C) 0.9544
D) 0.9772
E) 0.9987

F) A) and E)
G) A) and C)

Correct Answer

verifed

verified

A popular tool for planning and scheduling simple projects, and for initial planning on more complex projects, is the:


A) activity-on-arrows network
B) activity-on-nodes network
C) Gantt chart
D) critical path method
E) program evaluation and review technique

F) D) and E)
G) B) and D)

Correct Answer

verifed

verified

C

Deterministic networks use three time estimates - shortest, most likely and longest - for each activity in order to best determine the activity's estimated time.

A) True
B) False

Correct Answer

verifed

verified

What activities make up the critical path?

Correct Answer

verifed

verified

Critical p...

View Answer

What is the estimated expected (mean) time for project completion?


A) 35 weeks
B) 39 weeks
C) 50 weeks
D) 104 weeks
E) 105 weeks

F) B) and E)
G) B) and D)

Correct Answer

verifed

verified

C

The expected duration of this project is:


A) 12
B) 17
C) 20
D) 36
E) 77

F) B) and D)
G) C) and D)

Correct Answer

verifed

verified

What is the estimated slack time for activity A?


A) 0 days
B) 20 days
C) 40 days
D) 60 days
E) 100 days

F) C) and D)
G) All of the above

Correct Answer

verifed

verified

Good project management is especially important with virtual teams.

A) True
B) False

Correct Answer

verifed

verified

There are four activities on the critical path.Coincidentally, their standard deviations are all equal to 4.The standard deviation of the critical path is therefore equal to:


A) 2
B) 4
C) 8
D) 16
E) 64

F) B) and E)
G) C) and D)

Correct Answer

verifed

verified

What is the estimated expected (mean) time for activity E?


A) 91 days
B) 99 days
C) 100 days
D) 101 days
E) 115 days

F) B) and D)
G) B) and E)

Correct Answer

verifed

verified

Simulation can be used for cases in which network activity times are dependent.

A) True
B) False

Correct Answer

verifed

verified