Activity 4-5 in a network diagram has an optimistic time estimate of five days, a most likely time estimate of seven days, and a pessimistic time estimate of 10 days.Its expected time is approximately:


A) 5
B) 6
C) 7
D) 8
E) 9

F) All of the above
G) A) and D)

Correct Answer

verifed

verified

Shortening activity durations is called:


A) Expediting
B) Crashing
C) Vendor management
D) Null nodes
E) Trade-off analysis

F) B) and C)
G) B) and D)

Correct Answer

verifed

verified

Path probabilities are calculated by dividing path mean by path standard deviations.

A) True
B) False

Correct Answer

verifed

verified

What is the estimated slack time for activity D?


A) 0 days
B) 30 days
C) 40 days
D) 50 days
E) 100 days

F) A) and B)
G) D) and E)

Correct Answer

verifed

verified

What is the total cost of reducing this project by two weeks?

Correct Answer

verifed

verified

Total cost...

View Answer

What is the critical path for this project network?

Correct Answer

verifed

verified

Events 1-2...

View Answer

The costs associated with risk events tend to be lower near the beginning of a project, and higher near the end of the project.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is not characteristic of good risk management?


A) estimating the likelihood of chance events occurring.
B) planning to eliminate chance events.
C) identifying potential chance events.
D) formulating contingency plans in the event of chance events.
E) analyzing the consequences of chance events.

F) B) and E)
G) A) and E)

Correct Answer

verifed

verified

A method used for establishing a logical framework for identifying the required activities for the project is called:


A) Work breakdown structure
B) PERT
C) planning matrix
D) crashing
E) critical path analysis

F) D) and E)
G) C) and E)

Correct Answer

verifed

verified

An advantage of Gantt charts in project management is that they identify which activities can be delayed without delaying the overall project.

A) True
B) False

Correct Answer

verifed

verified

Project management software eliminates conflicts when there are shared resources.

A) True
B) False

Correct Answer

verifed

verified

The higher the node number, the longer the activity will take.

A) True
B) False

Correct Answer

verifed

verified

The critical path for the network shown is:


A) a-c-g
B) a-d-f-g
C) a-d-h-i
D) b-e-f-g
E) b-e-h-i

F) A) and B)
G) C) and E)

Correct Answer

verifed

verified

Which of the following is not true about the use of dummy activities in project networking?


A) They preserve the separate identities of activities.
B) They clarify precedence relationships among activities.
C) They have an activity time equal to zero.
D) They have an activity time variance equal to zero.
E) They are used in activities-on-nodes (AON) network diagrams.

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

In the project network presented below, numbers on each arrow refer to the expected time and standard deviation in weeks for that particular activity.For example, "8,2" indicates an activity with an expected time of 8 and a standard deviation of two weeks.

Correct Answer

verifed

verified

blured image For this project, determine each of the...

View Answer

Consider the portion of a project depicted by this graph: Consider the portion of a project depicted by this graph:   What is the latest start time of activity 6-7 if the latest finish of activity 7-8 is 26, and the latest finish of activity 7-9 is 23? A) 18 B) 17 C) 13 D) 12 E) 10 What is the latest start time of activity 6-7 if the latest finish of activity 7-8 is 26, and the latest finish of activity 7-9 is 23?


A) 18
B) 17
C) 13
D) 12
E) 10

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

One way that project management differs from management of more traditional activities is because of the limited lifetime of projects.

A) True
B) False

Correct Answer

verifed

verified

What is the estimated expected (mean) time for project completion?


A) 160 days
B) 170 days
C) 200 days
D) 210 days
E) 300 days

F) C) and E)
G) All of the above

Correct Answer

verifed

verified

What is the estimated standard deviation in the time for activity E?


A) 0 weeks
B) 1 week
C) 2 weeks
D) 3 weeks
E) 4 weeks

F) C) and E)
G) B) and E)

Correct Answer

verifed

verified

What is the estimated expected (mean) time for Activity E?


A) 31 weeks
B) 38 weeks
C) 39 weeks
D) 40 weeks
E) 43 weeks

F) B) and C)
G) B) and D)

Correct Answer

verifed

verified