Filters
Question type

Study Flashcards

The output of MRP is:


A) gross requirements
B) net requirements
C) a schedule of requirements for all parts and end items
D) inventory reorder points
E) economic order quantities and reorder points

F) A) and E)
G) C) and D)

Correct Answer

verifed

verified

The multiplication process used by MRP to determine lower level requirements is called:


A) time-phasing
B) pegging
C) netting
D) projecting
E) exploding

F) B) and D)
G) None of the above

Correct Answer

verifed

verified

Net requirements for component J are as follows: 60 units in week 2, 40 units in week 3, and 60 units in week 5.If a fixed-period, three-period lot-sizing method is used, what will be the quantity of the first planned receipt?


A) 60
B) 100
C) 160
D) Cannot be determined
E) None of the above

F) B) and C)
G) A) and E)

Correct Answer

verifed

verified

The inventory records contain information on the status of each item by time period.

A) True
B) False

Correct Answer

verifed

verified

If 40 Ps are needed, and on-hand inventory consists of 15 Ps and 10 each of all other components and subassemblies, how many Cs are needed?


A) 340
B) 350
C) 380
D) 400
E) 590

F) B) and C)
G) B) and D)

Correct Answer

verifed

verified

In an MRP master schedule, the planning horizon is often separated into a series of times periods called:


A) pegging
B) lead times
C) stacked lead times
D) time buckets
E) firm, fixed and frozen

F) None of the above
G) A) and E)

Correct Answer

verifed

verified

Lot-for-lot ordering in MRP eliminates the holding costs for parts that are carried over to other periods.

A) True
B) False

Correct Answer

verifed

verified

When MRP II systems include feedback, they are known as:


A) MRPIII
B) Enterprise resource planning
C) Circular MRP
D) Feasible MRP
E) Closed Loop MRP

F) A) and D)
G) B) and E)

Correct Answer

verifed

verified

ERP implementation probably won't require:


A) cross functional teams
B) just a few weeks to install
C) intensive training
D) high funding for both initial cost and maintenance
E) frequent upgrades after installation

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Which of these items would be most likely to have dependent demand?


A) Xbox batteries
B) toy trains
C) flowers
D) chocolate chip cookies
E) wrist watches

F) A) and E)
G) C) and E)

Correct Answer

verifed

verified

The following is a list of components required to produce one unit of end item P: P: 2 A's, 3 B's, 3 C's A: 5 M's, 2 R's B: 1 D, 3 N's. C: 1 T, 4 N's M: 1 N Determine the number of N's that will be needed to make 60 P's in each of these cases: (A) There are currently 10 P's on hand. (B) On-hand inventory consists of 15 P's, 10A's, 20 B's, 10 C's, 100 N's, 300 T's, and 200 M's.

Correct Answer

verifed

verified

The product-structure tree: blured image A) [1 N per...

View Answer

Lot-for-lot ordering in MRP provides coverage for some predetermined number of periods using forecasted demand to extend beyond the orders already received for those periods.

A) True
B) False

Correct Answer

verifed

verified

Comparing known and expected capacity requirements with projected capacity availability is the job of _______.


A) planned releases
B) load reports
C) lot sizing
D) work loading
E) time fencing

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

ERP automates the tasks involved in performing a business process, such as order fulfillment and financial reporting.

A) True
B) False

Correct Answer

verifed

verified

In MRP, "scheduled receipts" are:


A) identical to "planned-order receipts"
B) identical to "planned-order releases"
C) open orders (that is, ordered before the first time bucket, but not delivered yet)
D) "net requirements"
E) available to promise inventory

F) B) and E)
G) None of the above

Correct Answer

verifed

verified

Capacity requirements planning (CRP) is an important feature in MRP+.

A) True
B) False

Correct Answer

verifed

verified

Project Management approaches can help in a conversion to an ERP system.

A) True
B) False

Correct Answer

verifed

verified

MRP, considering inventory position, bills of material, open purchase orders and lead times guarantees a feasible production plan if the inputs to MRP are accurate.

A) True
B) False

Correct Answer

verifed

verified

Given the following information, construct a product tree diagram and develop a material requirements plan that will lead to 400 units of product P being available at the start of week 7.

Correct Answer

verifed

verified

ERP's primary value comes from applications ________.


A) deployment
B) development
C) interfaces
D) integration
E) networking

F) B) and C)
G) A) and E)

Correct Answer

verifed

verified

Showing 21 - 40 of 89

Related Exams

Show Answer