The MRP input listing the assemblies, subassemblies, parts, and raw materials needed to produce one unit of finished product is the:


A) master production schedule
B) bill-of-materials
C) inventory-records
D) assembly-time chart
E) net-requirements chart

F) A) and C)
G) A) and B)

Correct Answer

verifed

verified

Which of these products would be most likely to have dependent demand?


A) refrigerators
B) automobile engines
C) televisions
D) brownies
E) automobiles

F) B) and C)
G) A) and D)

Correct Answer

verifed

verified

In MRP, EOQ models tend to be less useful for materials at the lowest levels than for upper level assemblies of the bill of materials since higher-level assemblies have larger dollar investments.

A) True
B) False

Correct Answer

verifed

verified

A recent effort to expand the scope of production resource planning by involving other functional areas in the planning process has been:


A) material requirements planning
B) capacity requirements planning
C) manufacturing resources planning
D) Just-In-Time planning
E) multifunctional relationships planning

F) A) and D)
G) D) and E)

Correct Answer

verifed

verified

Under lot-for-lot, order sizes for component parts are essentially determined directly from which one of the following?


A) gross requirements
B) net requirements
C) economic order quantity
D) gross requirements - net requirements
E) net requirements - amount on-hand

F) B) and C)
G) B) and E)

Correct Answer

verifed

verified

The development and application of MRP depended upon two developments: (1) the recognition of the difference between independent and dependent demand, and (2) :


A) computers
B) development of the EOQ model
C) inventory control systems
D) blanket purchase orders
E) the internet

F) B) and E)
G) B) and D)

Correct Answer

verifed

verified

End item Alpha's product structure tree and inventory information are as follows:

Correct Answer

verifed

verified

blured image (A) If 50 units of Alpha are to be asse...

View Answer

Which one of the following most closely describes the MRP approach that is used for components or subassemblies to compensate for variations in lead time?


A) pegging
B) safety stock
C) increased order sizes
D) safety time
E) low-level coding

F) C) and D)
G) B) and E)

Correct Answer

verifed

verified

MRP works best if the inventory items have dependent demand.

A) True
B) False

Correct Answer

verifed

verified

_______ is choosing how many to order or make.


A) Quantity determination
B) Package sizing
C) Lot sizing
D) Grouping
E) Aggregation

F) A) and E)
G) B) and E)

Correct Answer

verifed

verified

Load reports show capacity requirements for departments or work centers which may be more or less than the capacity available in that work center.

A) True
B) False

Correct Answer

verifed

verified

The master schedule needs to be for a period long enough to cover the stacked or cumulative lead time necessary to produce the end items.

A) True
B) False

Correct Answer

verifed

verified

Which of the following most closely describes dependent demand?


A) demand generated by suppliers
B) estimates of demand using regression analysis of independent variables
C) derived demand
D) demands placed on suppliers by their customers
E) net material requirements

F) A) and C)
G) B) and E)

Correct Answer

verifed

verified

Initially, a master production schedule - the output from MRP - may not represent a feasible schedule.

A) True
B) False

Correct Answer

verifed

verified

The bill of materials contains information on lead times and current inventory position on every component required to produce the end item.

A) True
B) False

Correct Answer

verifed

verified

An MRP system whose records are updated continuously is referred to as a(n) :


A) regenerative system
B) batch-type system
C) Plossl-Wright system
D) net-change system
E) gross-change system

F) A) and E)
G) B) and C)

Correct Answer

verifed

verified

ERP began in manufacturing organizations but has spread into service organizations.

A) True
B) False

Correct Answer

verifed

verified

In MRP, the gross requirements of a given component part are calculated from:


A) net requirements + amount on-hand.
B) gross requirements of the immediate parent.
C) planned orders of the end item.
D) net requirements of end item.
E) planned orders of the immediate parent.

F) A) and B)
G) C) and D)

Correct Answer

verifed

verified

Independent demand tends to be more 'lumpy' than dependent demand meaning that we need large quantities followed by periods of no demand.

A) True
B) False

Correct Answer

verifed

verified

When should an order for Carved Chocolate Eggs be released?


A) at the start of week 2
B) at the start of week 3
C) at the start of week 4
D) at the start of week 5
E) at the start of week 6

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified