A) These are two different names for essentially the same technique.
B) CPM tends to focus more on the critical path; PERT focuses on the parallel paths.
C) PERT gives a clearer indication of activity slack, while CPM gives a better picture of path slack.
D) Because of its recent discovery, much less is known about CPM than PERT.
E) CPM is useful for project manager selection; PERT is useful for project team selection.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) I and II
B) I, II, and III
C) I and III
D) II and III
E) I only
Correct Answer
verified
Multiple Choice
A) II; IV
B) III; IV
C) I; III
D) I; II
E) II; III
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 30 days
B) 29 days
C) 38 days
D) 26 days
E) 35 days
Correct Answer
verified
Multiple Choice
A) 0.6826
B) 0.8413
C) 0.9544
D) 0.9772
E) 0.9987
Correct Answer
verified
Multiple Choice
A) essentially theoretical.
B) its adaptability.
C) its symmetry.
D) It is bimodal.
E) It can easily be converted to a normal distribution.
Correct Answer
verified
Multiple Choice
A) early in; most costly
B) late in; least costly
C) late in; most costly
D) before the beginning of; most complex
E) at the conclusion of; least complex
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Short Answer
Correct Answer
verified
Multiple Choice
A) 0 days
B) 2 days
C) 3 days
D) 4 days
E) 12 days
Correct Answer
verified
Multiple Choice
A) 0 days
B) 20 days
C) 40 days
D) 60 days
E) 100 days
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) a-c-g.
B) a-d-f-g.
C) a-d-h-i.
D) b-e-f-g.
E) b-e-h-i.
Correct Answer
verified
Short Answer
Correct Answer
verified
Showing 101 - 120 of 137
Related Exams