Filters
Question type

Study Flashcards

Concerning PERT and CPM:


A) These are two different names for essentially the same technique.
B) CPM tends to focus more on the critical path; PERT focuses on the parallel paths.
C) PERT gives a clearer indication of activity slack, while CPM gives a better picture of path slack.
D) Because of its recent discovery, much less is known about CPM than PERT.
E) CPM is useful for project manager selection; PERT is useful for project team selection.

F) All of the above
G) A) and B)

Correct Answer

verifed

verified

If the expected length of a path is more than 2.5 standard deviations less than a desired project completion time, the path will not be a factor in assessing the probability of finishing the project on time.

A) True
B) False

Correct Answer

verifed

verified

The earliest finish time for an activity is equal to the latest finish time minus the activity time.

A) True
B) False

Correct Answer

verifed

verified

Which of the following are limitations of PERT? (I) Time estimates may include a fudge factor. (II) Important activities may be overlooked. (III) It is an after-the-fact analysis.


A) I and II
B) I, II, and III
C) I and III
D) II and III
E) I only

F) None of the above
G) A) and D)

Correct Answer

verifed

verified

Suppose a project is subject to the following risk events (each with a given probability of occurring and a cost associated with that occurrence) :  Event  Probability  Cost ($000 s)  I .253 II .654 III .112 IV .321\begin{array} { l l l } \text { Event } & \text { Probability } & \text { Cost } ( \$ 000 \mathrm {~s} ) \\\text { I } & .2 & 53 \\\text { II } & .6 & 54 \\\text { III } & .1 & 12 \\\text { IV } & .3 & 21\end{array} Given these, Event _____ should probably get the most attention and Event _____ should probably get the least.


A) II; IV
B) III; IV
C) I; III
D) I; II
E) II; III

F) A) and E)
G) A) and D)

Correct Answer

verifed

verified

The standard deviation of the critical path is equal to the sum of the standard deviations of all of the activities on the critical path.

A) True
B) False

Correct Answer

verifed

verified

Consider the following work breakdown structure:  Duration Estimates (Days)   Activity  Precedes  Optimistic  Most Likely  Pessimistic  Start  U, V  U  W 355065 V  W, X 284052 W  Z 263544 X  Y 284052 Y  Z 262938 Z  End 366084\begin{array}{r}\text { Duration Estimates (Days) }\quad\quad\quad\\\begin{array} { l c c c c } \text { Activity } & \text { Precedes } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { Start } & \text { U, V } & - & - & - \\\text { U } & \text { W } & 35 & 50 & 65 \\\text { V } & \text { W, X } & 28 & 40 & 52 \\\text { W } & \text { Z } & 26 & 35 & 44 \\\text { X } & \text { Y } & 28 & 40 & 52 \\\text { Y } & \text { Z } & 26 & 29 & 38 \\\text { Z } & \text { End } & 36 & 60 & 84\end{array}\end{array} What is the estimated expected (mean) time for activity Y?


A) 30 days
B) 29 days
C) 38 days
D) 26 days
E) 35 days

F) A) and D)
G) B) and D)

Correct Answer

verifed

verified

Consider the following work breakdown structure:  Time Estimates (days)   Activity  Precedes  Optimistic  Most Likely  Pessimistic  Start  A, B, C  A  D 385062 B  E 9099108 C  End 85100115 D  F 192531 E  End 91100115 F  End 626568\begin{array}{l}\begin{array} { c c c c c } &&&\text { Time Estimates (days) }\\\text { Activity } & \text { Precedes } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { Start } & \text { A, B, C } & - & - & - \\\text { A } & \text { D } & 38 & 50 & 62 \\\text { B } & \text { E } & 90 & 99 & 108 \\\text { C } & \text { End } & 85 & 100 & 115 \\\text { D } & \text { F } & 19 & 25 & 31 \\\text { E } & \text { End } & 91 & 100 & 115 \\\text { F } & \text { End } & 62 & 65 & 68\end{array}\end{array} What is the probability that this project will be completed within 205 days?


A) 0.6826
B) 0.8413
C) 0.9544
D) 0.9772
E) 0.9987

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

The basis for use of the beta distribution in PERT is:


A) essentially theoretical.
B) its adaptability.
C) its symmetry.
D) It is bimodal.
E) It can easily be converted to a normal distribution.

F) C) and D)
G) A) and C)

Correct Answer

verifed

verified

Project risk events tend to be unlikely __________ a project, but that's also when they tend to be the __________.


A) early in; most costly
B) late in; least costly
C) late in; most costly
D) before the beginning of; most complex
E) at the conclusion of; least complex

F) C) and E)
G) All of the above

Correct Answer

verifed

verified

Activity D has an optimistic time of three days, a pessimistic time of nine days, and a most likely time of four days. Determine its expected time and variance.

Correct Answer

verifed

verified

te = (to + 4tm + tp)/6 =...

View Answer

Slack time is equal to LS-ES or LF-EF.

A) True
B) False

Correct Answer

verifed

verified

The project computing algorithm requires both a forward and a backward pass.

A) True
B) False

Correct Answer

verifed

verified

The task of identifying risks should involve everyone associated with the project.

A) True
B) False

Correct Answer

verifed

verified

Consider the following work breakdown structure:  Duration Estimate (Days)  Start  Finish  Activity  Node  Node  Optimistic  Most Likely  Pessimistic  A 1291521 B 13132123 C 246918 D 25233547 E 35192627 F 46232941 G 56142026 H 67258\begin{array}{r} \text { Duration Estimate (Days) }\quad \quad \quad \quad \\\begin{array}{lccccc} & \text { Start } & \text { Finish } \\\text { Activity } & \text { Node } & \text { Node } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { A } & 1 & 2 & 9 & 15 & 21 \\\text { B } & 1 & 3 & 13 & 21 & 23 \\\text { C } & 2 & 4 & 6 & 9 & 18 \\\text { D } & 2 & 5 & 23 & 35 & 47 \\\text { E } & 3 & 5 & 19 & 26 & 27 \\\text { F } & 4 & 6 & 23 & 29 & 41 \\\text { G } & 5 & 6 & 14 & 20 & 26 \\\text { H } & 6 & 7 & 2 & 5 & 8\end{array}\end{array} Within what amount of time (in weeks) is there a 90 percent probability that the critical path for this project will be completed? 95 percent? 99 percent?

Correct Answer

verifed

verified

Consider the following work breakdown structure:  Start  Finish  Duration (Days)   Activity  Node  Node  Optimistic  Most Likely  Pessimistic  A 12415059 B 13546066 C 24587082 D 34324144\begin{array}{cccccc}&\text { Start }&\text { Finish }&&\text { Duration (Days) } \\\text { Activity } & \text { Node } & \text { Node } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { A } & 1 & 2 & 41 & 50 & 59 \\\text { B } & 1 & 3 & 54 & 60 & 66 \\\text { C } & 2 & 4 & 58 & 70 & 82 \\\text { D } & 3 & 4 & 32 & 41 & 44\end{array} What is the estimated standard deviation in the time for activity D?


A) 0 days
B) 2 days
C) 3 days
D) 4 days
E) 12 days

F) B) and E)
G) All of the above

Correct Answer

verifed

verified

Consider the following work breakdown structure:  Time Estimates (days)   Activity  Precedes  Optimistic  Most Likely  Pessimistic  Start  A, B, C  A  D 385062 B  E 9099108 C  End 85100115 D  F 192531 E  End 91100115 F  End 626568\begin{array}{l}\begin{array} { c c c c c } &&&\text { Time Estimates (days) }\\\text { Activity } & \text { Precedes } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { Start } & \text { A, B, C } & - & - & - \\\text { A } & \text { D } & 38 & 50 & 62 \\\text { B } & \text { E } & 90 & 99 & 108 \\\text { C } & \text { End } & 85 & 100 & 115 \\\text { D } & \text { F } & 19 & 25 & 31 \\\text { E } & \text { End } & 91 & 100 & 115 \\\text { F } & \text { End } & 62 & 65 & 68\end{array}\end{array} What is the estimated slack time for activity A?


A) 0 days
B) 20 days
C) 40 days
D) 60 days
E) 100 days

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

The path in a network with the average length of time to completion is called the critical path.

A) True
B) False

Correct Answer

verifed

verified

A project is represented by the following diagram: A project is represented by the following diagram:   The critical path for the network shown is: A)  a-c-g. B)  a-d-f-g. C)  a-d-h-i. D)  b-e-f-g. E)  b-e-h-i. The critical path for the network shown is:


A) a-c-g.
B) a-d-f-g.
C) a-d-h-i.
D) b-e-f-g.
E) b-e-h-i.

F) B) and C)
G) B) and E)

Correct Answer

verifed

verified

Consider the following work breakdown structure:  Duration Estimate (Days)  Start  Finish  Activity  Node  Node  Optimistic  Most Likely  Pessimistic  A 1291521 B 13132123 C 246918 D 25233547 E 35192627 F 46232941 G 56142026 H 67258\begin{array}{r} \text { Duration Estimate (Days) }\quad \quad \quad \quad \\\begin{array}{lccccc} & \text { Start } & \text { Finish } \\\text { Activity } & \text { Node } & \text { Node } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { A } & 1 & 2 & 9 & 15 & 21 \\\text { B } & 1 & 3 & 13 & 21 & 23 \\\text { C } & 2 & 4 & 6 & 9 & 18 \\\text { D } & 2 & 5 & 23 & 35 & 47 \\\text { E } & 3 & 5 & 19 & 26 & 27 \\\text { F } & 4 & 6 & 23 & 29 & 41 \\\text { G } & 5 & 6 & 14 & 20 & 26 \\\text { H } & 6 & 7 & 2 & 5 & 8\end{array}\end{array} What is the estimated standard deviation (in weeks) for the critical path completion time?

Correct Answer

verifed

verified

Showing 101 - 120 of 137

Related Exams

Show Answer