In MRP, scheduled receipts are:


A) identical to planned-order receipts.
B) identical to planned-order releases.
C) open orders (that is, ordered before the first time bucket, but not delivered yet) .
D) net requirements.
E) available-to-promise inventory.

F) A) and B)
G) B) and E)

Correct Answer

verifed

verified

Capacity requirements planning is an important feature in MRP+.

A) True
B) False

Correct Answer

verifed

verified

The MRP input listing the assemblies, subassemblies, parts, and raw materials needed to produce one unit of finished product is the:


A) master production schedule.
B) bill of materials.
C) inventory records.
D) assembly time chart.
E) net requirements chart.

F) B) and D)
G) A) and E)

Correct Answer

verifed

verified

A bill of materials contains a listing of all the assemblies, parts, and materials needed to produce one unit of an end item.

A) True
B) False

Correct Answer

verifed

verified

End item Alpha's product structure tree and inventory information are as follows: End item Alpha's product structure tree and inventory information are as follows:   (A) If 50 units of Alpha are to be assembled, how many additional units of S will be needed? All parts can be ordered using lot-for-lot ordering, except M, which must be ordered in multiples of 40 units. [Hint: You don't need to do an MRP plan.] (B) An order for 100 units of Alpha is scheduled to be shipped at the start of week 9. When is the earliest that any particular component must be started so that the order for Alpha will be ready to ship? [Hint: You don't need to do an MRP plan.] (A) If 50 units of Alpha are to be assembled, how many additional units of S will be needed? All parts can be ordered using lot-for-lot ordering, except M, which must be ordered in multiples of 40 units. [Hint: You don't need to do an MRP plan.] (B) An order for 100 units of Alpha is scheduled to be shipped at the start of week 9. When is the earliest that any particular component must be started so that the order for Alpha will be ready to ship? [Hint: You don't need to do an MRP plan.]

Correct Answer

verifed

verified

(A) Gross requirements for S a...

View Answer

Lumpy demand for components results primarily from the periodic scheduling of batch production.

A) True
B) False

Correct Answer

verifed

verified

MRP can apply to services, especially when it is focused on: (I) work-in-process inventory. (II) finished goods inventory. (III) service components. (IV) materials that are part of the service process.


A) II and IV only
B) I and III only
C) I, II, and IV only
D) I, III, and IV only
E) III and IV only

F) B) and E)
G) A) and D)

Correct Answer

verifed

verified

The multiplication process used by MRP to determine lower-level requirements is called:


A) time-phasing.
B) pegging.
C) netting.
D) projecting.
E) exploding.

F) A) and B)
G) All of the above

Correct Answer

verifed

verified

Refer to this product tree: Refer to this product tree:   If 17 Ps are needed, and on-hand inventory consists of 10 As, 15 Bs, 20 Cs, 12 Ms, and 5 Ns, how many Cs are needed? A)  48 B)  144 C)  192 D)  212 E)  272 If 17 Ps are needed, and on-hand inventory consists of 10 As, 15 Bs, 20 Cs, 12 Ms, and 5 Ns, how many Cs are needed?


A) 48
B) 144
C) 192
D) 212
E) 272

F) A) and C)
G) A) and E)

Correct Answer

verifed

verified

The MRP input storing information on the status of each item by time period (e.g., scheduled receipts, lead time, lot size) is the:


A) master production schedule.
B) bill of materials.
C) inventory records.
D) assembly time chart.
E) net requirements chart.

F) C) and D)
G) All of the above

Correct Answer

verifed

verified

_______ is choosing how many to order or make.


A) Quantity determination
B) Package sizing
C) Lot sizing
D) Grouping
E) Aggregation

F) All of the above
G) A) and B)

Correct Answer

verifed

verified

Bunny Helpers, Inc., has just received an order for 100 Deluxe Easter Baskets, which must be ready for delivery at the start of week 6. An MRP planner has prepared the following table showing product structure, lead times (orders are lot-for-lot) , and quantities on hand:  Deluxe Easter Basket BOM  Lead Time  On-Hand  Deluxe Easter Basket 1 week 10 Dark Chocolate Truffles (2 per)  2 weeks 30 Carved Chocolate Eggs (4 per)  1 week 50\begin{array} { c l l } \text { Deluxe Easter Basket BOM } & \text { Lead Time } & \text { On-Hand } \\\hline \text { Deluxe Easter Basket } & 1 \text { week } & 10 \\\text { Dark Chocolate Truffles (2 per) } & 2 \text { weeks } & 30 \\\text { Carved Chocolate Eggs (4 per) } & 1 \text { week } & 50\end{array} Each Deluxe Basket contains two dark chocolate truffles and four carved chocolate eggs; additionally one bottle of Alka-Seltzer is included for those who overindulge. What is the net requirement for dark chocolate truffles to fill this order?


A) 100
B) 140
C) 150
D) 180
E) 200

F) None of the above
G) B) and D)

Correct Answer

verifed

verified

In MRP, under lot-for-lot ordering, planned-order receipts are:


A) identical to scheduled receipts.
B) identical to planned-order releases.
C) open orders (that is, ordered before the first time bucket, but not delivered yet) .
D) gross requirements.
E) available-to-promise inventory.

F) D) and E)
G) C) and D)

Correct Answer

verifed

verified

The gross requirements value for any given component is equal to the net requirements of that component's immediate parent multiplied by the quantity per parent.

A) True
B) False

Correct Answer

verifed

verified

MRP II is simply an improved version of MRP that processes more quickly and can plan for a larger number of end items.

A) True
B) False

Correct Answer

verifed

verified

Net requirements for component J are as follows: 60 units in week 2, 40 units in week 3, and 60 units in week 5. If a fixed-period, three-period lot-sizing method is used, what will be the quantity of the first planned receipt?


A) 60
B) 100
C) 160
D) cannot be determined
E) none of the choices

F) None of the above
G) B) and E)

Correct Answer

verifed

verified

In MRP, EOQ models tend to be less useful for materials at the lowest levels than for upper-level assemblies of the bill of materials since higher-level assemblies have larger dollar investments.

A) True
B) False

Correct Answer

verifed

verified

MRP output reports are divided into two main groups, daily and weekly.

A) True
B) False

Correct Answer

verifed

verified

ERP implementation probably will not require:


A) cross-functional teams.
B) just a few weeks to install.
C) intensive training.
D) high funding for both initial cost and maintenance.
E) frequent upgrades after installation.

F) D) and E)
G) A) and C)

Correct Answer

verifed

verified

Bunny Helpers, Inc., has just received an order for 100 Deluxe Easter Baskets, which must be ready for delivery at the start of week 6. An MRP planner has prepared the following table showing product structure, lead times (orders are lot-for-lot) , and quantities on hand:  Deluxe Easter Basket BOM  Lead Time  On-Hand  Deluxe Easter Basket 1 week 10 Dark Chocolate Truffles (2 per)  2 weeks 30 Carved Chocolate Eggs (4 per)  1 week 50\begin{array} { c l l } \text { Deluxe Easter Basket BOM } & \text { Lead Time } & \text { On-Hand } \\\hline \text { Deluxe Easter Basket } & 1 \text { week } & 10 \\\text { Dark Chocolate Truffles (2 per) } & 2 \text { weeks } & 30 \\\text { Carved Chocolate Eggs (4 per) } & 1 \text { week } & 50\end{array} Each Deluxe Basket contains two dark chocolate truffles and four carved chocolate eggs; additionally one bottle of Alka-Seltzer is included for those who overindulge. If the firm is using a fixed-period lot size of two periods, what is the order size for the first order?


A) 120
B) 200
C) 280
D) 160
E) 150

F) A) and D)
G) C) and D)

Correct Answer

verifed

verified