On a log-log graph, learning curves appear as:


A) upward-curving lines.
B) downward-curving lines.
C) straight lines.
D) lines which increase at a decreasing rate.
E) lines which decrease at a decreasing rate.

F) A) and E)
G) A) and D)

Correct Answer

verifed

verified

A manager wants to analyze the learning curve associated with producing one of his company's products. Accordingly, he has gathered the following data:  UNIT PRODUCED  TIME REQUIRED  Second 5 hours  Fourth 4 hours \begin{array} { | l | l | } \hline \text { UNIT PRODUCED } &{ \text { TIME REQUIRED } } \\\hline \text { Second } & 5 \text { hours } \\\hline \text { Fourth } & 4 \text { hours } \\\hline\end{array} Approximately how long will it take to produce the fifth through tenth units?


A) 15 hours
B) 16 hours
C) 18 hours
D) 20 hours
E) 21 hours

F) A) and E)
G) All of the above

Correct Answer

verifed

verified

An 80 percent learning curve means that with each doubling of repetitions there will be a 20 percent decrease in time per unit.

A) True
B) False

Correct Answer

verifed

verified

If we have never made the first unit but only think we know how much the labor time will be, we cannot draw a learning curve.

A) True
B) False

Correct Answer

verifed

verified

A job has an 80 percent learning curve. The second unit required 12 hours to complete. Approximately how many hours will be devoted to the first five units (including those already completed) ?


A) 26
B) 36
C) 46
D) 56
E) 66

F) All of the above
G) A) and E)

Correct Answer

verifed

verified

A manager wants to analyze the learning curve associated with producing one of his company's products. Accordingly, he has gathered the following data:  UNIT PRODUCED  TIME REQUIRED  Second 5 hours  Fourth 4 hours \begin{array} { | l | l | } \hline \text { UNIT PRODUCED } & { \text { TIME REQUIRED } } \\\hline \text { Second } & 5 \text { hours } \\\hline \text { Fourth } & 4 \text { hours } \\\hline\end{array} Approximately how long did it take to produce the first four units?


A) 15 hours
B) 16 hours
C) 18 hours
D) 20 hours
E) 21 hours

F) A) and B)
G) A) and E)

Correct Answer

verifed

verified

Negotiated purchasing results in lower unit costs for smaller quantities.

A) True
B) False

Correct Answer

verifed

verified

Once production is underway and the learning curve effect is occurring, successive changes made to the production process will cause the time per unit to:


A) continue following the original learning curve without any impact.
B) cause a scallop effect.
C) increase the unit time and result in a higher percentage learning curve.
D) decrease the unit time and result in a higher percentage learning curve.
E) decrease the unit time and result in a lower percentage learning curve.

F) B) and D)
G) C) and D)

Correct Answer

verifed

verified

Learning curves generally apply to situations in which there is a high degree of human involvement and tasks are fairly repetitive.

A) True
B) False

Correct Answer

verifed

verified

The decrease in time between the second and fourth units will be equal to the decrease in time between the first and second units.

A) True
B) False

Correct Answer

verifed

verified

Suppose the first unit required 800 hours and the second unit required only 680. Which of the following times for the fourth unit would be consistent with a true learning curve scenario?


A) 492
B) 587
C) 578
D) 603
E) 583

F) B) and D)
G) C) and D)

Correct Answer

verifed

verified

Learning curves are used primarily for mass production applications.

A) True
B) False

Correct Answer

verifed

verified

The more __________ a task, the less likely it is that a substantial learning curve will be in effect.


A) strategic
B) capital intensive
C) routine
D) tactical
E) unusual

F) A) and B)
G) B) and C)

Correct Answer

verifed

verified

Sally suspects strongly that there is a learning curve associated with solving problems assigned for operations management. She notes that it took her approximately 33 minutes to solve the first problem and 17 minutes to solve the fifth problem. (A) Estimate Sally's learning percentage. (B) Using your answer from part A, estimate how long it will take Sally to finish the three remaining problems.

Correct Answer

verifed

verified

(A) T1 (unit factor 5) = T5. T...

View Answer

A manager wants to analyze the learning curve associated with producing one of his company's products. Accordingly, he has gathered the following data:  UNIT PRODUCED  TIME REQUIRED  Second 5 hours  Fourth 4 hours \begin{array} { | l | l | } \hline \text { UNIT PRODUCED } & { \text { TIME REQUIRED } } \\\hline \text { Second } & 5 \text { hours } \\\hline \text { Fourth } & 4 \text { hours } \\\hline\end{array} Approximately how long will it take to produce the 10th unit?


A) 1 hour
B) 2 hours
C) 3 hours
D) 4 hours
E) 5 hours

F) None of the above
G) A) and B)

Correct Answer

verifed

verified

An order we just received has a 90 percent learning curve associated with it. The second unit of the total 25-unit order had a unit time of 36 minutes. What will the total time be for the entire order (all 25 units)?

Correct Answer

verifed

verified

The total time will ...

View Answer

In which of the following managerial activities would learning curves probably be the least useful?


A) negotiated purchasing
B) manpower planning
C) location analysis
D) budgeting
E) pricing new products

F) C) and E)
G) All of the above

Correct Answer

verifed

verified

To which of the following challenges are learning curves important considerations?


A) capacity planning
B) product designs
C) process layouts
D) output-based compensation
E) demand forecasting

F) D) and E)
G) A) and B)

Correct Answer

verifed

verified

When are learning curves most relevant to managerial decision making in mass production settings?


A) late in product life cycles
B) in the maturity phase
C) in the decline phase
D) before processes are stabilized
E) never

F) C) and E)
G) B) and D)

Correct Answer

verifed

verified

The learning curve is a basic tool for mass production-type activities because it can deal with large volumes of output.

A) True
B) False

Correct Answer

verifed

verified