Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) These are two different names for essentially the same technique.
B) CPM tends to focus more on the critical path.
C) PERT gives a better indication of activity slack,CPM a better picture of path slack.
D) Because of its recent discovery,much less is known about CPM that PERT.
E) All of the above are true.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) observed and predicted times.
B) optimistic and pessimistic times.
C) latest finish and latest start times.
D) earliest finish and earliest start times.
E) latest start and earliest start times.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 135 days.
B) 145 days.
C) 170 days.
D) 180 days.
E) 255 days.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 0.6826.
B) 0.8413.
C) 0.9544.
D) 0.9772.
E) 0.9987.
Correct Answer
verified
Multiple Choice
A) 3 days.
B) 5 days.
C) 9 days.
D) 16 days.
E) 25 days.
Correct Answer
verified
Multiple Choice
A) 35 days.
B) 36 days.
C) 39 days.
D) 40 days.
E) 45 days.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 11 days.
B) 20 days.
C) 18 days.
D) 22 days.
E) 15 days.
Correct Answer
verified
Showing 41 - 60 of 93
Related Exams