Projects involve routine activities that are performed repeatedly.

A) True
B) False

Correct Answer

verifed

verified

In PERT,the path with the fewest activities is referred to as the critical path.

A) True
B) False

Correct Answer

verifed

verified

Concerning PERT and CPM:


A) These are two different names for essentially the same technique.
B) CPM tends to focus more on the critical path.
C) PERT gives a better indication of activity slack,CPM a better picture of path slack.
D) Because of its recent discovery,much less is known about CPM that PERT.
E) All of the above are true.

F) D) and E)
G) A) and D)

Correct Answer

verifed

verified

A common assumption when using PERT/Cost is that the costs are incurred at a constant rate throughout the duration of an activity.

A) True
B) False

Correct Answer

verifed

verified

A normal distribution is usually used to describe the form of the probability distribution of activity durations in the PERT three-estimate approach.

A) True
B) False

Correct Answer

verifed

verified

A forward pass is the process of moving forward through the project network to determine the latest start times and latest finish times of each activity.

A) True
B) False

Correct Answer

verifed

verified

When calculating the probability that a project will finish by a certain time,the approximation that is obtained is usually lower than the true probability.

A) True
B) False

Correct Answer

verifed

verified

In project network analysis,slack refers to the difference between:


A) observed and predicted times.
B) optimistic and pessimistic times.
C) latest finish and latest start times.
D) earliest finish and earliest start times.
E) latest start and earliest start times.

F) A) and B)
G) None of the above

Correct Answer

verifed

verified

Although PERT and CPM were originally developed for somewhat different types of projects,they are now nearly identical in terms of analysis and procedures.

A) True
B) False

Correct Answer

verifed

verified

If two paths are tied for the longest duration,both would be considered to be critical paths.

A) True
B) False

Correct Answer

verifed

verified

Figure Figure   (time in days)  -What is the estimated mean time for project completion? A) 135 days. B) 145 days. C) 170 days. D) 180 days. E) 255 days. (time in days) -What is the estimated mean time for project completion?


A) 135 days.
B) 145 days.
C) 170 days.
D) 180 days.
E) 255 days.

F) B) and E)
G) C) and D)

Correct Answer

verifed

verified

The latest finish of an activity is the earliest late start of any immediately preceding activity.

A) True
B) False

Correct Answer

verifed

verified

The length of the critical path is determined by adding the expected completion times for all the activities in the project.

A) True
B) False

Correct Answer

verifed

verified

A Gantt chart of a project shows the scheduled start and finish times for activities.

A) True
B) False

Correct Answer

verifed

verified

The values assigned to the nodes in a project network are there to identify the precedence relationships.

A) True
B) False

Correct Answer

verifed

verified

Figure Figure   (time in days)  -What is the probability that this project will be completed within 205 days? A) 0.6826. B) 0.8413. C) 0.9544. D) 0.9772. E) 0.9987. (time in days) -What is the probability that this project will be completed within 205 days?


A) 0.6826.
B) 0.8413.
C) 0.9544.
D) 0.9772.
E) 0.9987.

F) A) and C)
G) B) and C)

Correct Answer

verifed

verified

There are four activities on the critical path,and they have standard deviations of 1,2,4,and 2 days.The standard deviation of the critical path is:


A) 3 days.
B) 5 days.
C) 9 days.
D) 16 days.
E) 25 days.

F) C) and D)
G) A) and C)

Correct Answer

verifed

verified

Figure Figure   (time in days)  -What is the estimated mean time for activity E? A) 35 days. B) 36 days. C) 39 days. D) 40 days. E) 45 days. (time in days) -What is the estimated mean time for activity E?


A) 35 days.
B) 36 days.
C) 39 days.
D) 40 days.
E) 45 days.

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

A manager has decided that an activity has a pessimistic estimate of 15 days,a most-likely estimate of 6 days,and an optimistic estimate of 3 days.The expected duration of this activity is 6 days.

A) True
B) False

Correct Answer

verifed

verified

Figure Figure   -The duration of the critical path is: A) 11 days. B) 20 days. C) 18 days. D) 22 days. E) 15 days. -The duration of the critical path is:


A) 11 days.
B) 20 days.
C) 18 days.
D) 22 days.
E) 15 days.

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified