Filters
Question type

Study Flashcards

The labor standard for a product was 5.5 hours at a wage rate of $9 per hour. The firm produced 1,020 units of the item. Labor costs totaled $50,414 and 5,540 hours of labor were used. An analysis of labor costs would indicate


A) a $554 favorable labor rate variance.
B) a $630 unfavorable labor time variance.
C) a $554 unfavorable labor rate variance.
D) a $630 favorable labor time variance.

E) A) and B)
F) None of the above

Correct Answer

verifed

verified

Variance analysis is a tool used by management to pinpoint inefficiencies in the manufacturing process.

A) True
B) False

Correct Answer

verifed

verified

The general model for computing a price variance is:


A) (actual price - standard price) x standard quantity of inputs.
B) (actual price - standard price) x actual quantity of inputs.
C) (actual quantity of inputs - standard quantity of units) x standard price.
D) (actual quantity - standard quantity) x actual price.

E) None of the above
F) A) and D)

Correct Answer

verifed

verified

The labor time (efficiency)variance and the labor------------ variance together make up the total labor variance.

Correct Answer

verifed

verified

The production manager is accountable for all material quantity variances as defective product and scrap is a result of inexperienced workers.

A) True
B) False

Correct Answer

verifed

verified

WinterRec uses a standard cost system. The following data is available for November: WinterRec uses a standard cost system. The following data is available for November:   The actual direct labor rate for November is: A) $9.25 per hour. B) $9.63 per hour. C) $9.40 per hour. D) $9.00 per hour. The actual direct labor rate for November is:


A) $9.25 per hour.
B) $9.63 per hour.
C) $9.40 per hour.
D) $9.00 per hour.

E) None of the above
F) A) and B)

Correct Answer

verifed

verified

Better Blankets, Inc. makes a SnuggieBlank using flannel material and trim binding. They have instituted a successful JIT system and thus no longer have to stock inventory prior to their production need. The Standard Cost Card for The SnuggieBlank model is shown. STANDARD COST CARD Better Blankets, Inc. makes a SnuggieBlank using flannel material and trim binding. They have instituted a successful JIT system and thus no longer have to stock inventory prior to their production need. The Standard Cost Card for The SnuggieBlank model is shown.  STANDARD COST CARD   The company reported the following results concerning January:   - The labor efficiency variance in January is: A)  $3,050 favorable.	 B)  $1,600 unfavorable. C)  $1,600 favorable. D)  $3,050 unfavorable.  The company reported the following results concerning January: Better Blankets, Inc. makes a SnuggieBlank using flannel material and trim binding. They have instituted a successful JIT system and thus no longer have to stock inventory prior to their production need. The Standard Cost Card for The SnuggieBlank model is shown.  STANDARD COST CARD   The company reported the following results concerning January:   - The labor efficiency variance in January is: A)  $3,050 favorable.	 B)  $1,600 unfavorable. C)  $1,600 favorable. D)  $3,050 unfavorable.  - The labor efficiency variance in January is:


A) $3,050 favorable.
B) $1,600 unfavorable.
C) $1,600 favorable.
D) $3,050 unfavorable.

E) B) and C)
F) A) and B)

Correct Answer

verifed

verified

The standard costs for a unit of product are shown below.  Materials: 4 pounds at $1.80 per pound $7.20 Labor: 80 hours at $13.00 per hour 10.40 Overhead: 65% of direct labor 6.76\begin{array} { l l r } \text { Materials: } & 4 \text { pounds at } \$ 1.80 \text { per pound } & \$ 7.20 \\\text { Labor: } & 80 \text { hours at } \$ 13.00 \text { per hour } & 10.40 \\\text { Overhead: } & 65 \% \text { of direct labor } & 6.76\end{array} During July, Job N-5 for 200 units was completed. The actual costs of the job are shown below.  Materials: 823 pourds at $1.86 per pound $1,530.78 Lubor: 157 hours at $13.13 per hour 2,061.41 Overhead Applied: 65% of direct labor 1,339.92\begin{array} { l l r } \text { Materials: } & 823 \text { pourds at } \$ 1.86 \text { per pound } & \$ 1,530.78 \\\text { Lubor: } & 157 \text { hours at } \$ 13.13 \text { per hour } & 2,061.41 \\\text { Overhead Applied: } & 65 \% \text { of direct labor } & 1,339.92\end{array} 1. What is the total cost variance between actual cost and standard cost? 2. What is the total material variance? 3. What is the material quantity variance? 4. What is the material price variance?

Correct Answer

verifed

verified

1.$60.11 unfavorable...

View Answer

The difference between the total standard cost and the total actual cost is the


A) cost variance.
B) labor rate variance.
C) materials price variance.
D) standard cost card amount.

E) All of the above
F) A) and B)

Correct Answer

verifed

verified

An increase in the activity level will result in:


A) an increase in fixed unit cost.
B) an increase in unit variable cost.
C) a decrease in unit variable cost.
D) decrease in fixed unit cost.

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

If the predetermined overhead application rate is a percentage of labor cost, then a favorable labor time variance will be accompanied by a favorable manufacturing overhead variance.

A) True
B) False

Correct Answer

verifed

verified

Prepare a budget for manufacturing costs for Nacelle Manufacturing for the month of July 2019 from the following information. Direct materials are estimated to be $480,000 for the year and direct labor is estimated to be $96,000. The direct labor per hour average is $13 and the budgeted level of activity for the month is 1,200 hours. Prepare a budget for manufacturing costs for Nacelle Manufacturing for the month of July 2019 from the following information. Direct materials are estimated to be $480,000 for the year and direct labor is estimated to be $96,000. The direct labor per hour average is $13 and the budgeted level of activity for the month is 1,200 hours.     Prepare a budget for manufacturing costs for Nacelle Manufacturing for the month of July 2019 from the following information. Direct materials are estimated to be $480,000 for the year and direct labor is estimated to be $96,000. The direct labor per hour average is $13 and the budgeted level of activity for the month is 1,200 hours.

Correct Answer

verifed

verified

Nacelle Manufacturin...

View Answer

Semi-variable costs vary in direct proportion to the volume of activity or production.

A) True
B) False

Correct Answer

verifed

verified

The controllable overhead variance compares the actual overhead costs incurred with what the costs should have been for the units produced.

A) True
B) False

Correct Answer

verifed

verified

The range of activity at which the factory is likely to operate is referred to as the--------- range of activity.

Correct Answer

verifed

verified

To measure manufacturing efficiency, it is necessary to first identify costs behavior and separate cost into their behavioral components.

A) True
B) False

Correct Answer

verifed

verified

Better Blankets, Inc. makes a SnuggieBlank using flannel material and trim binding. They have instituted a successful JIT system and thus no longer have to stock inventory prior to their production need. The Standard Cost Card for The SnuggieBlank model is shown. STANDARD COST CARD Better Blankets, Inc. makes a SnuggieBlank using flannel material and trim binding. They have instituted a successful JIT system and thus no longer have to stock inventory prior to their production need. The Standard Cost Card for The SnuggieBlank model is shown.  STANDARD COST CARD   The company reported the following results concerning January:   - The variable overhead efficiency variance in January is: A) $3,000 favorable. B) $2,000 unfavorable. C) $2,000 favorable. D) $3,000 unfavorable. The company reported the following results concerning January: Better Blankets, Inc. makes a SnuggieBlank using flannel material and trim binding. They have instituted a successful JIT system and thus no longer have to stock inventory prior to their production need. The Standard Cost Card for The SnuggieBlank model is shown.  STANDARD COST CARD   The company reported the following results concerning January:   - The variable overhead efficiency variance in January is: A) $3,000 favorable. B) $2,000 unfavorable. C) $2,000 favorable. D) $3,000 unfavorable. - The variable overhead efficiency variance in January is:


A) $3,000 favorable.
B) $2,000 unfavorable.
C) $2,000 favorable.
D) $3,000 unfavorable.

E) B) and C)
F) A) and C)

Correct Answer

verifed

verified

Costs that tend to change in total directly with the volume of manufacturing activity are called------------costs.

Correct Answer

verifed

verified

Which of the following would NOT be considered a fixed manufacturing cost?


A) depreciation using straight-line.
B) insurance.
C) utilities.
D) taxes.

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

The materials price variance for an item is the difference between its actual price and its standard cost


A) divided by the actual quantity.
B) multiplied by the standard quantity allowed.
C) multiplied by the difference between the actual quantity and the standard quantity.
D) multiplied by the actual quantity used.

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

Showing 101 - 120 of 126

Related Exams

Show Answer