A) Using overtime
B) Hiring more workers
C) Using specialized equipment
D) All of the above
E) None of the above
Correct Answer
verified
Multiple Choice
A) When do activities need to start and finish to meet a deadline?
B) How much delay can be tolerated for certain activities?
C) Given uncertainties,what is the probability that a project will finish on time?
D) What is the least expensive way to expedite a project to meet a deadline?
E) All of the above
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 30 days
B) 29 days
C) 38 days
D) 26 days
E) 35 days
Correct Answer
verified
Multiple Choice
A) A-E-H
B) B-H
C) A-D-G
D) C-F-H
E) C-I-J
Correct Answer
verified
Multiple Choice
A) 22
B) 23
C) 24
D) 25
E) 26
Correct Answer
verified
Multiple Choice
A) 3
B) 4
C) 9
D) 10
E) 12
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 5 days
B) 6 days
C) 7 days
D) 8 days
E) 9 days
Correct Answer
verified
Multiple Choice
A) These are two different names for essentially the same technique
B) CPM tends to focus more on the critical path
C) PERT gives a better indication of activity slack,CPM a better picture of path slack
D) Because of its recent discovery,much less is known about CPM that PERT
E) All of the above are true
Correct Answer
verified
Multiple Choice
A) 0 5000
B) 0 8413
C) 0 9544
D) 0 9772
E) 0 9987
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 13
B) 15
C) 20
D) 52
E) 81
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) the total cost of crashing the project
B) the total of the durations of the activities on the critical path
C) the latest finish time of the finish node
D) the total number of activities on the critical path e None of the above
Correct Answer
verified
Showing 21 - 40 of 92