Which of the following are ways of crashing an activity?


A) Using overtime
B) Hiring more workers
C) Using specialized equipment
D) All of the above
E) None of the above

F) C) and D)
G) None of the above

Correct Answer

verifed

verified

PERT/CPM can answer which of the following questions?


A) When do activities need to start and finish to meet a deadline?
B) How much delay can be tolerated for certain activities?
C) Given uncertainties,what is the probability that a project will finish on time?
D) What is the least expensive way to expedite a project to meet a deadline?
E) All of the above

F) B) and E)
G) A) and E)

Correct Answer

verifed

verified

A project manager does not need to monitor each individual activity,just the overall project when looking at budget costs

A) True
B) False

Correct Answer

verifed

verified

-What is the estimated mean time for activity Y?


A) 30 days
B) 29 days
C) 38 days
D) 26 days
E) 35 days

F) A) and D)
G) C) and D)

Correct Answer

verifed

verified

The path with the greatest slack is:


A) A-E-H
B) B-H
C) A-D-G
D) C-F-H
E) C-I-J

F) C) and E)
G) None of the above

Correct Answer

verifed

verified

51 51   A) 22  B) 23  C) 24  D) 25  E) 26


A) 22
B) 23
C) 24
D) 25
E) 26

F) B) and D)
G) A) and D)

Correct Answer

verifed

verified

52 52   A) 3  B) 4  C) 9  D) 10  E) 12


A) 3
B) 4
C) 9
D) 10
E) 12

F) None of the above
G) A) and D)

Correct Answer

verifed

verified

Only activities on the critical path are initial candidates for crashing

A) True
B) False

Correct Answer

verifed

verified

Crashing cannot be accomplished by using different materials than originally planned

A) True
B) False

Correct Answer

verifed

verified

Activity C in a project network has an optimistic time estimate of five days,a most likely time estimate of seven days,and a pessimistic time estimate of nine days Its expected duration is approximately:


A) 5 days
B) 6 days
C) 7 days
D) 8 days
E) 9 days

F) A) and B)
G) B) and E)

Correct Answer

verifed

verified

Concerning PERT and CPM:


A) These are two different names for essentially the same technique
B) CPM tends to focus more on the critical path
C) PERT gives a better indication of activity slack,CPM a better picture of path slack
D) Because of its recent discovery,much less is known about CPM that PERT
E) All of the above are true

F) B) and C)
G) A) and E)

Correct Answer

verifed

verified

What is the probability that the critical path will be completed within 210 days?


A) 0 5000
B) 0 8413
C) 0 9544
D) 0 9772
E) 0 9987

F) A) and E)
G) A) and C)

Correct Answer

verifed

verified

The standard deviation of the critical path is equal to the sum of the standard deviations of all the activities on the critical path

A) True
B) False

Correct Answer

verifed

verified

  -The expected duration of this project is: A) 13  B) 15  C) 20  D) 52  E) 81 -The expected duration of this project is:


A) 13
B) 15
C) 20
D) 52
E) 81

F) B) and D)
G) C) and D)

Correct Answer

verifed

verified

The activities with the longest durations in a project network are called critical activities

A) True
B) False

Correct Answer

verifed

verified

The values assigned to the nodes in a project network are there to identify the precedence relationships

A) True
B) False

Correct Answer

verifed

verified

Crashing an activity will always reduce the duration of a project

A) True
B) False

Correct Answer

verifed

verified

The latest starting time for an activity is equal to the latest finish time minus the duration of the activity

A) True
B) False

Correct Answer

verifed

verified

Activities that are not on the critical path have a slack time equal to zero

A) True
B) False

Correct Answer

verifed

verified

When using linear programming to make crashing decisions,the objective is to minimize:


A) the total cost of crashing the project
B) the total of the durations of the activities on the critical path
C) the latest finish time of the finish node
D) the total number of activities on the critical path e None of the above

E) C) and D)
F) B) and C)

Correct Answer

verifed

verified