A) forecasting
B) combined
C) complex
D) simulation
E) break-even
Correct Answer
verified
Multiple Choice
A) $548.58
B) $551.62
C) $604.16
D) $638.23
E) $640.25
Correct Answer
verified
Multiple Choice
A) less important the variable to the final outcome of the project.
B) less volatile the project's net present value to that variable.
C) greater the importance of accurately predicting the value of that variable.
D) greater the sensitivity of the project to the other variable inputs.
E) less volatile the project's outcome.
Correct Answer
verified
Multiple Choice
A) range of possible outcomes given that most variables are reliable only within a stated range.
B) degree to which the net present value reacts to changes in a single variable.
C) net present value range that can be realized from a proposed project.
D) degree to which a project relies on its fixed costs.
E) ideal ratio of variable costs to fixed costs for profit maximization.
Correct Answer
verified
Multiple Choice
A) operating at the accounting break-even point.
B) operating at the financial break-even point.
C) facing hard rationing.
D) operating with zero leverage.
E) operating at maximum capacity.
Correct Answer
verified
Multiple Choice
A) financial deferral.
B) financial allocation.
C) capital allocation.
D) marginal rationing.
E) hard rationing.
Correct Answer
verified
Multiple Choice
A) 4,871 units
B) 5,333 units
C) 5,415 units
D) 6,949 units
E) 7,248 units
Correct Answer
verified
Multiple Choice
A) I and III only
B) II and IV only
C) I,II,and III only
D) II,III,and IV only
E) I,II,III,and IV
Correct Answer
verified
Multiple Choice
A) $1,686,825
B) $1,496,250
C) $1,589,588
D) $1,593,500
E) $1,620,675
Correct Answer
verified
Multiple Choice
A) accounting break-even
B) leveraged break-even
C) marginal break-even
D) cash break-even
E) financial break-even
Correct Answer
verified
Multiple Choice
A) $47.65
B) $48.18
C) $54.02
D) $56.67
E) $62.50
Correct Answer
verified
Multiple Choice
A) Variable costs minus fixed costs equal marginal costs.
B) Variable costs are equal to fixed costs when production is equal to zero.
C) An increase in variable costs increases the operating cash flow.
D) Variable costs are inversely related to fixed costs.
E) Variable costs per unit are inversely related to the contribution margin per unit.
Correct Answer
verified
Multiple Choice
A) scenario
B) break-even
C) sensitivity
D) degree of operating leverage
E) simulation
Correct Answer
verified
Multiple Choice
A) financial rejection.
B) project rejection.
C) soft rationing.
D) marginal rationing.
E) capital rationing.
Correct Answer
verified
Multiple Choice
A) its maximum capacity.
B) the financial break-even point.
C) the cash break-even point.
D) the accounting break-even point.
E) a zero level of output.
Correct Answer
verified
Multiple Choice
A) 19.60 percent decrease
B) 16.03 percent decrease
C) 13.46 percent decrease
D) 5.60 percent decrease
E) 2.74 percent decrease
Correct Answer
verified
Multiple Choice
A) determination of the initial cash outlay required to implement a project.
B) determination of changes in NPV estimates when what-if questions are posed.
C) isolation of the effect that a single variable has on the NPV of a project.
D) separation of a project's sunk costs from its opportunity costs.
E) analysis of the effects that a project's terminal cash flows has on the project's NPV.
Correct Answer
verified
Multiple Choice
A) variable costs.
B) fixed costs.
C) sales.
D) operating cash flows.
E) net working capital.
Correct Answer
verified
Multiple Choice
A) $102,780
B) $104,640
C) $106,400
D) $108,000
E) $110,750
Correct Answer
verified
Multiple Choice
A) some proposed projects will be rejected.
B) some proposed projects will be temporarily delayed.
C) incorrect decisions will be made due to erroneous cash flow projections.
D) some projects will be mutually exclusive.
E) tax rates could change over the life of a project.
Correct Answer
verified
Showing 21 - 40 of 106
Related Exams