Filters
Question type

Which of the following statements is incorrect regarding variable overhead variances?


A) Variable overhead variances are based on the same general formulas used to compute the materials and labor price variances.
B) Variable overhead costs represent many inputs such as supplies, utilities and indirect labor.
C) All companies must calculate price and usage variances for variable overhead costs.
D) None of these answers is correct.

E) B) and C)
F) A) and D)

Correct Answer

verifed

verified

The Ferguson Company estimated that October sales would be 100,000 units with an average selling price of $6.00. Actual sales for October were 105,000 units and average selling price was $5.95.The sales revenue flexible budget variance was:


A) $5,000 favorable.
B) $5,000 unfavorable.
C) $5,250 favorable.
D) $5,250 unfavorable.

E) None of the above
F) A) and C)

Correct Answer

verifed

verified

Which of the following can reduce the amount of employees' budget gamesmanship?


A) Have superiors and subordinates participate in the standard-setting process.
B) Incorporate standards into the firm's evaluation system.
C) Avoid using standards for punitive purposes.
D) All of these answers are correct.

E) A) and B)
F) A) and D)

Correct Answer

verifed

verified

Management by exception means that only unfavorable cost variances are investigated.

A) True
B) False

Correct Answer

verifed

verified

Heartwood Company reported a $4,000 favorable direct labor price variance and a $1,500 unfavorable direct labor usage variance. Select the correct statement from the following.


A) It took the employees less time to produce the outputs than expected.
B) The total direct labor variance is $2,500 favorable.
C) The actual direct labor rate must have exceeded the standard direct labor rate.
D) It is probable that the supervisor attempted to use more highly skilled (and paid) employees than allowed for by the direct labor standards.

E) None of the above
F) A) and B)

Correct Answer

verifed

verified

The Russell Company provides the following standard cost data per unit of product: During the period, the company produced and sold 22,000 units incurring the following costs: The direct material price variance was:  Direct material ( 3 gallons (a) $6 per gallon)  $18.00 Direct labor ( 2 hours (a)  $10 per hour)  $20.00\begin{array} {| l|l| }\hline\text { Direct material ( } 3 \text { gallons }(a) \$ 6 \text { per gallon) }&\$18.00\\\hline\text { Direct labor ( } 2 \text { hours (a) } \$ 10 \text { per hour) }&\$20.00\\\hline\end{array}  Direct material68,000 gallons @$5.90 per gallon  Direct labor 45,500 hours a$9.75 per hour \begin{array} {| l|l| }\hline \text { Direct material}&68,000 \text { gallons } @ \$ 5.90 \text { per gallon }\\\hline\text { Direct labor }&45,500 \text { hours } a \$ 9.75 \text { per hour }\\\hline\end{array}


A) $6,600 unfavorable.
B) $6,600 favorable.
C) $6,800 unfavorable.
D) $6,800 favorable.

E) B) and C)
F) A) and D)

Correct Answer

verifed

verified

Cruz Company established a direct labor standard of 0.5 hour per unit at $12 per hour for one of its products. In April, Cruz produced 16,000 units and used 8,100 direct labor hours.Required: Based on this information, (a) Which variance can you calculate? (b) What is the dollar amount of the variance? (c) Is the variance favorable or unfavorable? (d) Do you consider the variance to be sufficiently material that managers should investigate to discover the cause of the variance?

Correct Answer

verifed

verified

(a) Labor usage variance
(b) Labor usage...

View Answer

Select the incorrect statement.


A) If both the flexible budget and actual results are based on the actual volume of activity, the flexible budget sales variance will be attributable to sales price, not sales volume.
B) Budget slack is the difference between deflated and realistic standards.
C) Gamesmanship is decreased if superiors and subordinates participate sincerely in setting mutually agreeable, attainable standards.
D) For performance evaluation, management should compare actual results to a flexible budget based on the actual volume of activity.

E) A) and D)
F) B) and C)

Correct Answer

verifed

verified

Multiplying the difference between actual materials price per unit and the standard materials price per unit by actual quantity of materials used is known as the:


A) Sales volume variance.
B) Materials price variance.
C) Labor price variance.
D) Materials usage variance.

E) B) and C)
F) None of the above

Correct Answer

verifed

verified

The Bach Company provides the following standard and actual cost relating to material price and labor usage.Based on the above information, which statement is correct?  Item to Classify Standard Actual  Materials Price 8.50 per gallon 8.35 per gallon  Labor Usage 30,000 hours 28.500 hours \begin{array}{lll}\text { Item to Classify }&\text {Standard}&\text { Actual }\\\text { Materials Price } & 8.50 \text { per gallon } & 8.35 \text { per gallon } \\\text { Labor Usage } & 30,000 \text { hours } & 28.500 \text { hours }\end{array}


A) Both the material price variance and the labor usage variance are unfavorable.
B) Both the materials price variance and the labor usage variance are favorable.
C) The labor usage variance is unfavorable.
D) The materials price variance is unfavorable.

E) A) and C)
F) All of the above

Correct Answer

verifed

verified

A static budget is one that shows estimated revenues and costs at multiple activity levels.

A) True
B) False

Correct Answer

verifed

verified

With respect to cost variances, managers seek to achieve actual costs that are higher than standard costs.

A) True
B) False

Correct Answer

verifed

verified

All of the following variances are unfavorable except?  Item to Classify Standard Actual  Sales volume 100.000 units 96.000 units  Sales price $4 per unit $3.90 per unit  Materials usage 40,000 gallons 42.000 gallons  Labor price 12.50 per Hour 12.45 per hour \begin{array}{ccc}\text { Item to Classify }&\text {Standard}&\text { Actual }\\\text { Sales volume } & 100.000 \text { units } & 96.000 \text { units } \\\text { Sales price } & \$ 4 \text { per unit } & \$ 3.90 \text { per unit } \\\text { Materials usage } & 40,000 \text { gallons } & 42.000 \text { gallons } \\\text { Labor price } & 12.50 \text { per Hour } & 12.45 \text { per hour }\end{array}


A) Materials usage
B) Sales price
C) Sales volume
D) Labor price

E) B) and D)
F) None of the above

Correct Answer

verifed

verified

The resources used in the manufacturing process are frequently called:


A) Variances.
B) Standards.
C) Inputs.
D) Outputs.

E) C) and D)
F) B) and C)

Correct Answer

verifed

verified

The total sales variance includes both price and volume variances.

A) True
B) False

Correct Answer

verifed

verified

Indicate whether each of the following statements is true or false.The difference between the actual fixed costs and budgeted fixed costs is the spending variance.For fixed costs, there is no flexible budget variance.Companies generally do not calculate a volume variance for fixed overhead costs.The volume variance is the difference between budgeted fixed cost and the applied fixed cost for the period.If the amount of fixed overhead applied to production is greater than the budgeted fixed overhead, the result is an unfavorable overhead volume variance.

Correct Answer

verifed

verified

The difference between the actual fixed ...

View Answer

Which of the following equations can be used to compute the total materials variance? (A = Actual; S = Standard; Q = Quantity; P = Price)


A) (AQ × AP) - (SQ × SP)
B) (SQ × SP) - (SQ × SP)
C) (AQ × AP) - (AQ × SP)
D) (AQ × SP) - (SQ × SP)

E) B) and D)
F) A) and B)

Correct Answer

verifed

verified

When a comparison of static and flexible budgets shows an unfavorable sales volume variance, the variable cost volume variances will also be unfavorable.

A) True
B) False

Correct Answer

verifed

verified

For a product made by George Company, last year's standards for labor were 2 hours at $12 per hour. Which of the following considerations should George take into account in setting the standards for this year?


A) George should revisit the prior year standards.
B) George should consider whether or not the prior year standards were achieved.
C) George should consider any changes that may influence worker productivity.
D) All of these answers are correct.

E) B) and D)
F) A) and B)

Correct Answer

verifed

verified

Standard cost systems facilitate the management practice known as:


A) Management by the numbers.
B) Management development.
C) Managing by exception.
D) Just-in-time management.

E) All of the above
F) B) and C)

Correct Answer

verifed

verified

Showing 61 - 80 of 154

Related Exams

Show Answer