Filters
Question type

Study Flashcards

Which statement regarding normal cash flows is correct?


A) If a project has "normal" cash flows, then its IRR must be positive.
B) If a project has "normal" cash flows, then its MIRR must be positive.
C) If a project has "normal" cash flows, then it will have exactly two real IRRs.
D) If a project has "normal" cash flows, then it can have only one real IRR, whereas a project with "non-normal" cash flows might have more than one real IRR.

E) A) and B)
F) A) and D)

Correct Answer

verifed

verified

Projects C and D are mutually exclusive and have normal cash flows. Project C has a higher NPV if the WACC is less than 12%, whereas Project D has a higher NPV if the WACC exceeds 12%. Which of the following statements is correct?


A) Project D has a higher IRR.
B) Project D is probably larger in scale than Project C.
C) Project C probably has a faster payback.
D) Project C has a higher IRR.

E) C) and D)
F) B) and C)

Correct Answer

verifed

verified

Normal Projects Q and R have the same NPV when the discount rate is zero. However, Project Q's cash flows come in faster than those of R. Therefore, we know that at any discount rate greater than zero, R will have a higher NPV than Q.

A) True
B) False

Correct Answer

verifed

verified

A decision to undertake significant downsizing to control fixed costs is usually made by senior management, with the decision reported to the firm's board of directors.

A) True
B) False

Correct Answer

verifed

verified

Under certain conditions, a project may have more than one IRR. One such condition is when, in addition to the initial investment at time = 0, a negative cash flow (or cost) occurs at the end of the project's life.

A) True
B) False

Correct Answer

verifed

verified

Projects A and B are mutually exclusive and have normal cash flows. Project A has an IRR of 15% and Project B's IRR is 20%. The company's WACC is 12%, and at that rate Project A has the higher NPV. Which of the following statements is correct?


A) The crossover rate for the two projects must be less than 12%.
B) Assuming the timing pattern of the two projects' cash flows is the same, Project B probably has a higher cost (and larger scale) .
C) Assuming the two projects have the same scale, Project B probably has a faster payback than Project A.
D) Since B has the higher IRR, then it must also have the higher NPV if the crossover rate is less than the WACC of 12%.

E) A) and C)
F) None of the above

Correct Answer

verifed

verified

Financing pressure or liquidity can explain the popular use of payback period in project appraisals for small firms.

A) True
B) False

Correct Answer

verifed

verified

Project S has a pattern of high cash flows in its early life, while Project L has a longer life, with large cash flows late in its life. Neither has negative cash flows after Year 0, and at the current cost of capital, the two projects have identical NPVs. Now, suppose interest rates and money costs decline. Other things held constant, this change will cause L to become preferred to S.

A) True
B) False

Correct Answer

verifed

verified

The level of detail needed to determine capital budget expenditures related to compliance with safety and/or environmental issues varies depending on the size and scope of the project(s).

A) True
B) False

Correct Answer

verifed

verified

Showing 61 - 69 of 69

Related Exams

Show Answer